📞 +91 98200 30685 ✉️
RERA: A51800043517

PADMALAXMI

by KEDAR BHIKAJI BAPAT Individual
Certificate Signed P51700000815
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700000815
Registration No.
REA51700005032
Registration Date
2017-07-24
Developer
KEDAR BHIKAJI BAPAT Individual
Architect
Mrugank Dixit
Project Bank
TJSB SAHAKARI BANK LTD
Proposed Possession
2018-03-31
Revised Possession
2018-03-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
624.00 sq.m
Total FSI
967.00
Approved FSI
840.00
MahaRERA QR
PADMALAXMI
MahaRERA — P51700000815
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🚗Open Parking10
🅿️Closed Parking8
📅Completion1900-01-01

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk 38.470001220703125 0 0 0
0%
1 Bhk 45.119998931884766 0 0 0
0%
1 Rk 24.829999923706055 0 0 0
0%
2 Bhk 51.5 0 0 0
0%
2 Bhk 51.68000030517578 0 0 0
0%
3 Bhk 61.2400016784668 0 0 0
0%

Padmalaxmi

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 38.47 1 1 0
100%
1 BHK 45.12 6 4 2
67%
1 RK 24.83 2 1 1
50%
2 BHK 51.5 5 4 1
80%
2 BHK 51.68 5 5 0
100%
3 BHK 61.24 1 1 0
100%

Construction Progress

PADMALAXMI

Basement (if any)100%

Padmalaxmi

Excavation100%

PADMALAXMI

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%

Padmalaxmi

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate15%

PADMALAXMI

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%

Padmalaxmi

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%
Overall Percentage of Completion of the work done For the entire Building /Wing71%

PADMALAXMI

Plinth100%
Podiums (if any) 0%

Padmalaxmi

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

PADMALAXMI

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Padmalaxmi

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90%

PADMALAXMI

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%

Padmalaxmi

Stilt Floor80%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply 50%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.