Parshuram Tulip

by Veritas Red Partnership
Certificate SignedPR1330002501373
Parshuram TulipProject photos will appear here when available.

Project Information

RERA Certificate No.
PR1330002501373
Registration No.
ACK21052500598
Registration Date
2025-10-31
Developer
Veritas Red Partnership
Project Bank
DCB BANK LIMITED
Proposed Possession
2028-06-28
Total Units
42
Units Sold
1 (2%)
Buildings
2
Project Area
894.90 sq.m
Total FSI
2967.37
Approved FSI
2661.91
MahaRERA QR
Parshuram Tulip
MahaRERA โ€” PR1330002501373
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable7
๐Ÿ”ขTotal Units21
๐ŸกResidential21
๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable7
๐Ÿ”ขTotal Units21
๐ŸกResidential21

Construction Progress

Wing A1 (Ashtaputre)

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Stilt Floor90%

Wing B1 (Arundhati)

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Stilt Floor90%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โœ…Energy managemcnt
โœ…Fire protection and fire safety requirements
โฌœInternal Roads & Footpaths
โœ…Landscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โœ…Solid Waste Management And Disposal
โœ…Storm Water Drains
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting