160
Units
2025
Possession
3
Buildings
Certificate Signed
Status
01Possession Timeline
Proposed
Dec 2025
Revised
Dec 2025
Status
Ongoing
02Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Type 1248–253 ftΒ²On request
Type 2248–253 ftΒ²On request
Office213–271 ftΒ²On request
Shop559–575 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03RERA Trust Record
MahaRERA No.
P51700005607
Registered
2021-09-09
Litigation
None on record
Escrow Bank
THE THANE BHARAT SAHAKARI BANK LIMITED
Architect
Aakruti Consultants
Total FSI
4330
04Buildings Β· 3 Wing(s)
Wing A9 floors Β· β€” units
Wing B9 floors Β· β€” units
Wing C9 floors Β· β€” units
05Land DNA Β· Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06Location
πŸ“ Bhiwandi
19.270151599999998,73.070042099999995
β–Έ Explore map & Street View β€” for verified buyers
07Promoter & Professionals
LAABH BUILDERS and DEVELOPERSNA
AAKRUTI CONSULTANTSArchitect
09Construction Progress71% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
10Amenities
Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationEnergy managemcntEnergy managementFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12Floor Plans, E-Brochure & Payment Plans
πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13EMI Calculator
β€”
14More by Laabh Builders And Developers
Laabh EnclaveThane West Β· Sold OutPehla GharThane West Β· Sold OutLaabh GloriaThane West Β· Sold Out
15MahaRERA projects nearby in Bhiwandi
Dgt - Sector 3A - Cluster 2 - Phase 11836 unitsDosti Greater Thane - Sector 3A - Cluster 1B - Phase 11025 unitsUsha Residency1020 unitsNarayani Dham Building No 2A And 2B869 unitsDgt - Sector 3A - Cluster 2 - Phase 2830 unitsDgt - Sector 3A - Cluster 2 - Phase 3710 unitsDosti Greater Thane - Sector 3A - Cluster 1B - Phase 3682 unitsSIYARA AVENUE620 unitsMagus City Tower 1 Selene431 unitsSiyara Viva423 unitsArihant Aaradhya Phase Ii412 unitsAtlantic377 units
?Frequently Asked Questions
When is possession of Pehla Ghar - Shiva Complex?

As per MahaRERA, proposed possession is Dec 2025, revised to Dec 2025.

Is Pehla Ghar - Shiva Complex RERA-registered?

Yes β€” MahaRERA registration P51700005607, registered 2021-09-09. No litigations on record.

Who is the developer?

Laabh Builders And Developers β€” 3 projects tracked on Mumbai Property Exchange.

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Bhiwandi β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
βœ“ MahaRERA P51700077356β˜… Featured
Lodha Group
Lodha Hanging Gardens, Dombivali
3 BHK, 4 BHK Β· β‚Ή16,400/sq.ft Β· Possession Dec 2027
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’