Project Information
RERA Certificate No.
P51700001716
Registration No.
REA51700006281
Developer
Ami Infra
Project Bank
BANK OF MAHARASHTRA
Proposed Possession
2020-04-30
Revised Possession
2020-10-30
Extended Possession
2022-04-30
Buildings
3
Project Area
3825.00 sq.m
Total FSI
5366.84
Approved FSI
454.33
Pink City Trident Phase 2
MahaRERA โ P51700001716
MahaRERA โ P51700001716
Scan to verify on MahaRERA portal
Wing-wise Details
๐
ฟ๏ธClosed Parking5
๐
Completion2020-04-30
๐
ฟ๏ธClosed Parking4
๐
Completion2020-04-30
๐
ฟ๏ธClosed Parking6
๐
Completion2020-04-30
Apartment Configurations
Wing A
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 31.29 | 14 | 13 | 1 | 93% |
| 1 BHK | 32.93 | 14 | 8 | 6 | 57% |
Wing B
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2 BHK | 42.95 | 47 | 34 | 13 | 72% |
| SHOP | 15.4 | 2 | 0 | 2 | 0% |
| SHOP | 16.27 | 2 | 0 | 2 | 0% |
| SHOP | 20.62 | 2 | 0 | 2 | 0% |
| SHOP | 21.31 | 2 | 0 | 2 | 0% |
Wing C
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK | 35.18 | 14 | 10 | 4 | 71% |
| 2 BHK | 41.32 | 14 | 7 | 7 | 50% |
| SHOP | 11.61 | 2 | 0 | 2 | 0% |
| SHOP | 12.29 | 1 | 0 | 1 | 0% |
| SHOP | 20.47 | 1 | 0 | 1 | 0% |
| SHOPS | 16.2 | 1 | 0 | 1 | 0% |
Construction Progress
Wing A
Wing B
Wing C
RERA Registered Amenities
โ
Aggregate area of recreational Open Space
โ
Community Buildings
โ
Electrical Meter Room, Sub-Station, Receiving Station
โฌEnergy management
โ
Fire Protection And Fire Safety
Requirements
โ
Landscaping & Tree Planting
โ
Open Parking
โ
Sewerage (Chamber, Lines, Septic Tank , STP)
โฌSolid Waste Management And Disposal
โ
Storm Water Drains
โ
Street Lighting
โฌTreatment And Disposal Of Sewage And Sullage Water
โ
Water Conservation, Rain water Harvesting
โ
Water Supply