RERA: A51800043517

Pink City Trident Phase 2

by Ami Infra
Kept in Abeyance P51700001716
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700001716
Registration No.
REA51700006281
Developer
Ami Infra
Project Bank
BANK OF MAHARASHTRA
Proposed Possession
2020-04-30
Revised Possession
2020-10-30
Extended Possession
2022-04-30
Buildings
3
Project Area
3825.00 sq.m
Total FSI
5366.84
Approved FSI
454.33
MahaRERA QR
Pink City Trident Phase 2
MahaRERA — P51700001716
Scan to verify on MahaRERA portal

Wing-wise Details

🅿️Closed Parking5
📅Completion2020-04-30
🅿️Closed Parking4
📅Completion2020-04-30
🅿️Closed Parking6
📅Completion2020-04-30

Apartment Configurations

Wing A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 31.29 14 13 1
93%
1 BHK 32.93 14 8 6
57%

Wing B

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 42.95 47 34 13
72%
SHOP 15.4 2 0 2
0%
SHOP 16.27 2 0 2
0%
SHOP 20.62 2 0 2
0%
SHOP 21.31 2 0 2
0%

Wing C

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 35.18 14 10 4
71%
2 BHK 41.32 14 7 7
50%
SHOP 11.61 2 0 2
0%
SHOP 12.29 1 0 1
0%
SHOP 20.47 1 0 1
0%
SHOPS 16.2 1 0 1
0%

Construction Progress

Wing A

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing70%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing B

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing60%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing C

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing70%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.