POONAM IMPERIA PHASE I

by POONAM SKYLINE CONSTRUCTION Partnership
Certificate SignedP99000017908

Project Information

RERA Certificate No.
P99000017908
Registration No.
REA99000044439
Registration Date
2023-02-14
Developer
POONAM SKYLINE CONSTRUCTION Partnership
Architect
Encon Architectural & Structural Works Project Consultants
Project Bank
HDFC BANK
Proposed Possession
2022-11-30
Revised Possession
1900-01-01
Extended Possession
2025-01-31
Units Sold
0
Buildings
4
Project Area
5273.71 sq.m
Total FSI
13216.00
Approved FSI
13216.00
MahaRERA QR
POONAM IMPERIA PHASE I
MahaRERA — P99000017908
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors15
Sanctioned15
🅿️Closed Parking44
📅Completion2022-05-31
🏗️Proposed Floors15
Sanctioned15
🅿️Closed Parking53
📅Completion2022-05-31
🏗️Proposed Floors15
Sanctioned15
🅿️Closed Parking45
📅Completion2022-05-31
🏗️Proposed Floors8
Sanctioned8
🚗Open Parking23
🅿️Closed Parking1
📅Completion2022-05-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Bhk32.810001373291016000
0%
1Bhk22.809999465942383000
0%
1Bhk30.979999542236328000
0%
1Bhk31.280000686645508000
0%
1Bhk31.959999084472656000
0%
1Bhk32.810001373291016000
0%
1Bhk32.900001525878906000
0%
1Bhk33.22999954223633000
0%
1Bhk33.310001373291016000
0%
1Bhk33.349998474121094000
0%
1Bhk33.90999984741211000
0%
1Bhk34.619998931884766000
0%
2Bhk40.11000061035156000
0%
2Bhk40.72999954223633000
0%
2Bhk40.869998931884766000
0%
2Bhk41.0000
0%
2Bhk41.13999938964844000
0%
2Bhk42.279998779296875000
0%

A Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.8126224
8%
1 BHK33.2328622
21%
2 BHK41.028424
14%
2 BHK41.1428622
21%

B Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.81261511
58%
1 BHK33.2314104
71%
1 BHK33.3114131
93%
2 BHK40.7314140
100%
2 BHK40.8728262
93%

C Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK32.91385
62%
1 BHK33.311376
54%
2 BHK40.1156551
98%

H Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK22.81110
100%
1 BHK30.98743
57%
1 BHK31.28642
67%
1 BHK31.96761
86%
1 BHK33.35541
80%
1 BHK33.91752
71%
1 BHK34.62725
29%
2 BHK42.28110
100%

Construction Progress

A WING

Basement (if any)100%

A Wing

Excavation100%

A WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

A Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%

A WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

A Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80%
Overall Percentage of Completion of the work done For the entire Building /Wing72%

A WING

Plinth100%
Podiums (if any) 0%

A Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

A WING

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

A Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

A WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

A Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

B WING

Basement (if any)100%

B Wing

Excavation100%

B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing89%

B WING

Plinth100%
Podiums (if any) 0%

B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises90%

B WING

Sanitary Fittings within the flats / premises90%
Slabs of Super Structure100%

B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

B Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

C WING

Basement (if any)100%

C Wing

Excavation100%

C WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

C Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

C WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

C Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing89%

C WING

Plinth100%
Podiums (if any) 0%

C Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises90%

C WING

Sanitary Fittings within the flats / premises90%
Slabs of Super Structure100%

C Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

C WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

C Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

H WING

Basement (if any)100%

H Wing

Excavation100%

H WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

H Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

H WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

H Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing89%

H WING

Plinth100%
Podiums (if any) 0%

H Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises90%

H WING

Sanitary Fittings within the flats / premises90%
Slabs of Super Structure100%

H Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

H WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

H Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station50%
Energy management
Fire Protection And Fire Safety Requirements50%
Landscaping & Tree Planting80%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply90%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.