📞 +91 98200 30685 ✉️
RERA: A51800043517

Rituworld Phase III M and N

by MOHAN HARDASMAL THARWANI Individual
Certificate Signed P51700006857
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700006857
Registration No.
REA51700015121
Registration Date
2021-09-10
Developer
MOHAN HARDASMAL THARWANI Individual
Architect
Arti V Jamgaonkar
Project Bank
PUNJAB NATIONAL BANK
Proposed Possession
2024-12-30
Revised Possession
2024-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
1401.04 sq.m
Total FSI
1566.36
Approved FSI
1566.36
MahaRERA QR
Rituworld Phase III M and N
MahaRERA — P51700006857
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
Sanctioned8
🅿️Closed Parking3
📅Completion2023-12-31
🏗️Proposed Floors9
Sanctioned9
🅿️Closed Parking10
📅Completion2023-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk 30.479999542236328 0 0 0
0%
1 Rk 21.239999771118164 0 0 0
0%

Wing M

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 30.48 20 1 19
5%
1 RK 21.24 6 0 6
0%

Wing N

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 30.48 28 12 16
43%

Construction Progress

WING M

Basement (if any)100%

Wing M

Excavation100%

WING M

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing M

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING M

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing M

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING M

Plinth100%
Podiums (if any) 0%

Wing M

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING M

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing M

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING M

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing M

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING N

Basement (if any)100%

Wing N

Excavation100%

WING N

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing N

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING N

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing N

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WING N

Plinth100%
Podiums (if any) 0%

Wing N

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WING N

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing N

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING N

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing N

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 60%
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 95%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 75%
Solid Waste Management And Disposal 100%
Storm Water Drains 95%
Street Lighting 95%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 95%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.