📞 +91 98200 30685 ✉️
RERA: A51800043517

SAI IMPERIA

by SADASHIV INFRA Partnership
Certificate Signed P51700005142
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700005142
Registration No.
REA51700012135
Registration Date
2017-08-09
Developer
SADASHIV INFRA Partnership
Architect
Manohar Mahadu Walimb
Project Bank
DOMBIVLI NAGARI SAHAKARI BANK LIMITED
Proposed Possession
2018-08-10
Revised Possession
2018-08-10
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
906.00 sq.m
Total FSI
1661.00
Approved FSI
1661.00
MahaRERA QR
SAI IMPERIA
MahaRERA — P51700005142
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
Sanctioned6
📅Completion2018-10-08

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 23.43000030517578 0 0 0
0%
1Bhk 25.34000015258789 0 0 0
0%
1Bhk 25.969999313354492 0 0 0
0%
1Bhk 25.979999542236328 0 0 0
0%
1Bhk 26.020000457763672 0 0 0
0%
1Bhk 27.489999771118164 0 0 0
0%
1Bhk 30.440000534057617 0 0 0
0%
1Rk 21.1200008392334 0 0 0
0%

Sai Imperia

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 23.43 4 0 4
0%
1 BHK 25.34 1 0 1
0%
1 BHK 25.97 8 2 6
25%
1 BHK 25.98 4 2 2
50%
1 BHK 26.02 4 3 1
75%
1 BHK 27.49 4 2 2
50%
1 BHK 30.44 4 1 3
25%
1RK 21.12 4 3 1
75%

Construction Progress

SAI IMPERIA

Basement (if any)100%

Sai Imperia

Excavation100%

SAI IMPERIA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.93%

Sai Imperia

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

SAI IMPERIA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Sai Imperia

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

SAI IMPERIA

Plinth100%
Podiums (if any) 0%

Sai Imperia

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises80%

SAI IMPERIA

Sanitary Fittings within the flats / premises80%
Slabs of Super Structure100%

Sai Imperia

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SAI IMPERIA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Sai Imperia

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing93%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply 70%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.