📞 +91 98200 30685 ✉️
RERA: A51800043517

Sai Satyam Homes

by Sai Satyam Developers Partnership
Certificate Signed P51700001809
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700001809
Registration No.
REA51700007582
Registration Date
2020-06-10
Developer
Sai Satyam Developers Partnership
Architect
Vitan Consultant
Project Bank
STATE BANK OF INDIA
Proposed Possession
2021-06-30
Revised Possession
2021-06-30
Extended Possession
2022-12-30
Units Sold
0
Buildings
3
Project Area
4390.00 sq.m
Total FSI
10527.00
Approved FSI
4318.00
MahaRERA QR
Sai Satyam Homes
MahaRERA — P51700001809
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors20
Sanctioned20
🅿️Closed Parking1
📅Completion2020-12-31
🏗️Proposed Floors20
Sanctioned20
🅿️Closed Parking1
📅Completion2020-12-31
🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking1
📅Completion1900-01-01

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 41.08000183105469 0 0 0
0%
Shop Type 1 15.399999618530273 0 0 0
0%
Shop Type 2 13.069999694824219 0 0 0
0%
Shop Type 3 12.399999618530273 0 0 0
0%
Tye 2 R 30.6299991607666 0 0 0
0%
Type 1 103.68000030517578 0 0 0
0%
Type 1 R 28.950000762939453 0 0 0
0%
Type 1 Residential 29.90999984741211 0 0 0
0%
Type 2 222.14999389648438 0 0 0
0%
Type 2 Residential 30.6200008392334 0 0 0
0%
Type 3 Residential 40.619998931884766 0 0 0
0%
Type 4 Residential 42.77000045776367 0 0 0
0%
Type3r 40.709999084472656 0 0 0
0%

Building A

Type Carpet (sq.ft) Total Booked Available Status
Tye 2 R 30.63 36 34 2
94%
Type 1 R 28.95 32 31 1
97%
Type3R 40.71 72 71 1
99%

Building B

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 41.08 7 6 1
86%
Shop Type 1 15.4 2 2 0
100%
Shop Type 2 13.07 2 1 1
50%
Shop Type 3 12.4 2 2 0
100%
Type 1 Residential 29.91 35 32 3
91%
Type 2 Residential 30.62 14 14 0
100%
Type 3 Residential 40.62 10 10 0
100%
Type 4 Residential 42.77 19 19 0
100%

Kdmc Building

Type Carpet (sq.ft) Total Booked Available Status
Type 1 103.68 1 0 1
0%
Type 2 222.15 4 0 4
0%

Construction Progress

Building A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Building B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

KDMC Building

Basement (if any)100%

Kdmc Building

Excavation100%

KDMC Building

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Kdmc Building

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

KDMC Building

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Kdmc Building

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

KDMC Building

Plinth100%
Podiums (if any) 0%

Kdmc Building

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

KDMC Building

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Kdmc Building

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

KDMC Building

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Kdmc Building

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.