Shankheshwar Crystal-Phase 1

by Shankheshwar Kreaters Partnership
Certificate SignedP51700000463
Shankheshwar Crystal-Phase 1Project photos will appear here when available.

Project Information

RERA Certificate No.
P51700000463
Registration No.
REA51700004627
Registration Date
2017-07-18
Developer
Shankheshwar Kreaters Partnership
Architect
Arc Anil R Nirgude
Project Bank
CENTRAL BANK OF INDIA
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
1057.57 sq.m
Total FSI
18652.57
Approved FSI
10362.57
MahaRERA QR
Shankheshwar Crystal-Phase 1
MahaRERA โ€” P51700000463
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors9
โœ…Sanctioned9
๐Ÿ—๏ธProposed Floors9
โœ…Sanctioned9
๐Ÿ—๏ธProposed Floors9
โœ…Sanctioned9

Apartment Configurations

BUILDING NO 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.6262602
97%

BUILDING NO 4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.62461234
26%
2 BHK44.151697
56%

BUILDING NO 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.62461630
35%
2 BHK44.1516313
19%

Construction Progress

BUILDING NO 3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space
โœ…CLUB HOUSE
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โœ…Energy managemcnt
โœ…Fire protection and fire safety requirements
โœ…Internal Roads & Footpaths50%
โœ…Landscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โฌœSolid Waste Management And Disposal
โœ…Storm Water Drains
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting