📞 +91 98200 30685 ✉️
RERA: A51800043517

Silver Spring

by M/s. Shri Venkatesh Ramdev Homes Partnership
Certificate Signed P51700006557
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700006557
Registration No.
REA51700013174
Registration Date
2023-03-06
Developer
M/s. Shri Venkatesh Ramdev Homes Partnership
Project Bank
IDBI BANK
Proposed Possession
2022-03-30
Revised Possession
2022-03-30
Extended Possession
2024-12-31
Units Sold
0
Buildings
2
Project Area
3780.00 sq.m
Total FSI
9739.46
Approved FSI
9739.46
MahaRERA QR
Silver Spring
MahaRERA — P51700006557
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors18
Sanctioned18
🚗Open Parking34
🅿️Closed Parking1
📅Completion2022-03-30
🏗️Proposed Floors19
Sanctioned19
⬇️Basements1
🚗Open Parking18
🅿️Closed Parking1
📅Completion2024-03-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 36.290000915527344 0 0 0
0%
1Bhk 36.369998931884766 0 0 0
0%
1Bhk 36.439998626708984 0 0 0
0%
2Bhk 55.209999084472656 0 0 0
0%
2Bhk 59.380001068115234 0 0 0
0%

Silver Spring Wing A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 36.29 15 11 4
73%
1 BHK 36.44 34 22 12
65%
2 BHK 59.38 34 30 4
88%

Silver Spring Wing C

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 36.37 32 31 1
97%
2 BHK 55.21 17 16 1
94%

Construction Progress

Silver Spring Wing A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70%
Overall Percentage of Completion of the work done For the entire Building /Wing58%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%
Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing80%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

SILVER SPRING WING C

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.