Simana - Wing B - Phase 1
by Bhoomi Properties
Partnership
Project Information
RERA Certificate No.
P51900033361
Registration No.
REA51900103007
Registration Date
2022-02-16
Developer
Bhoomi Properties Partnership
Architect
Hiren
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
292
Units Sold
160 (55%)
Buildings
1
Project Area
16494.93 sq.m
Total FSI
117738.73
Approved FSI
31560.85
Simana - Wing B - Phase 1
MahaRERA — P51900033361
MahaRERA — P51900033361
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors63
✅Sanctioned63
🏠Habitable63
🔢Total
Units292
🏡Residential292
⬇️Basements1
📅Completion2026-12-31
Apartment Configurations
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2.5Bhk | 87.5 | 0 | 0 | 0 | 0% |
| 2.5Bhk | 88.05000305175781 | 0 | 0 | 0 | 0% |
| 2.5Bhk | 88.69000244140625 | 0 | 0 | 0 | 0% |
| 2.5Bhk | 89.2300033569336 | 0 | 0 | 0 | 0% |
| 2.5Bhk | 92.12999725341797 | 0 | 0 | 0 | 0% |
| 2Bhk | 76.2300033569336 | 0 | 0 | 0 | 0% |
| 2Bhk | 76.77999877929688 | 0 | 0 | 0 | 0% |
| 2Bhk | 77.25 | 0 | 0 | 0 | 0% |
| 2Bhk | 77.80000305175781 | 0 | 0 | 0 | 0% |
| 2Bhk | 82.41999816894531 | 0 | 0 | 0 | 0% |
| 3Bhk | 104.70999908447266 | 0 | 0 | 0 | 0% |
| 3Bhk | 105.2699966430664 | 0 | 0 | 0 | 0% |
| 3Bhk | 105.61000061035156 | 0 | 0 | 0 | 0% |
| 3Bhk | 106.16999816894531 | 0 | 0 | 0 | 0% |
| 3Bhk | 109.31999969482422 | 0 | 0 | 0 | 0% |
| 3Bhk | 118.13999938964844 | 0 | 0 | 0 | 0% |
| 3Bhk | 118.80999755859375 | 0 | 0 | 0 | 0% |
| 3Bhk | 119.12000274658203 | 0 | 0 | 0 | 0% |
| 3Bhk | 119.37000274658203 | 0 | 0 | 0 | 0% |
| 3Bhk | 135.16000366210938 | 0 | 0 | 0 | 0% |
| 4Bhk | 166.10000610351562 | 0 | 0 | 0 | 0% |
| 5.5Bhk | 202.75 | 0 | 0 | 0 | 0% |
Simana - Wing B - Phase 1
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2 BHK | 76.23 | 26 | 16 | 10 | 62% |
| 2 BHK | 76.78 | 22 | 4 | 18 | 18% |
| 2 BHK | 77.25 | 16 | 0 | 16 | 0% |
| 2 BHK | 77.8 | 28 | 0 | 28 | 0% |
| 2 BHK | 82.42 | 6 | 0 | 6 | 0% |
| 2.5 BHK | 87.5 | 22 | 21 | 1 | 95% |
| 2.5 BHK | 88.05 | 18 | 12 | 6 | 67% |
| 2.5 BHK | 88.69 | 14 | 2 | 12 | 14% |
| 2.5 BHK | 89.23 | 24 | 1 | 23 | 4% |
| 2.5 BHK | 92.13 | 6 | 0 | 6 | 0% |
| 3 BHK | 104.71 | 22 | 17 | 5 | 77% |
| 3 BHK | 105.27 | 18 | 8 | 10 | 44% |
| 3 BHK | 105.61 | 14 | 1 | 13 | 7% |
| 3 BHK | 106.17 | 24 | 0 | 24 | 0% |
| 3 BHK | 109.32 | 6 | 0 | 6 | 0% |
| 3 BHK | 118.14 | 4 | 2 | 2 | 50% |
| 3 BHK | 118.81 | 2 | 2 | 0 | 100% |
| 3 BHK | 119.12 | 4 | 4 | 0 | 100% |
| 3 BHK | 119.37 | 4 | 0 | 4 | 0% |
| 3 BHK | 135.16 | 1 | 0 | 1 | 0% |
| 4 BHK | 166.1 | 4 | 0 | 4 | 0% |
| 5.5 BHK | 202.75 | 7 | 0 | 7 | 0% |
Construction Progress
Simana - Wing B - Phase 1
RERA Registered Amenities
✅
Aggregate area of recreational Open Space
✅
Club House and Swimming Pool
✅
Community Buildings
✅
Electrical Meter Room, Sub-Station, Receiving Station
✅
Energy management
✅
Fire Protection And Fire Safety
Requirements
✅
Landscaping & Tree Planting
✅
Open Parking
✅
Sewerage (Chamber, Lines, Septic Tank , STP)
✅
Solid Waste Management And Disposal
✅
Storm Water Drains
✅
Street Lighting
✅
Treatment And Disposal Of Sewage And Sullage Water
✅
Water Conservation, Rain water Harvesting
✅
Water Supply