📞 +91 98200 30685 ✉️
RERA: A51800043517

SM ELITE

by S M HITECH DEVELOPERS Partnership
Certificate Signed P52000052521
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P52000052521
Registration No.
REA52000141082
Registration Date
2023-09-08
Developer
S M HITECH DEVELOPERS Partnership
Architect
Destination Architecture Interior Design
Project Bank
AXIS BANK
Proposed Possession
2027-12-31
Units Sold
0
Project Area
4494.00 sq.m
Total FSI
13088.52
Approved FSI
12588.52
MahaRERA QR
SM ELITE
MahaRERA — P52000052521
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors14
Sanctioned14
⬇️Basements1
🅿️Closed Parking42
📅Completion2027-12-31
🏗️Proposed Floors14
Sanctioned14
⬇️Basements1
🅿️Closed Parking42
📅Completion2027-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2Bhk 48.119998931884766 0 0 0
0%
2Bhk 48.220001220703125 0 0 0
0%
2Bhk 50.540000915527344 0 0 0
0%
2Bhk 50.90999984741211 0 0 0
0%
3Bhk 64.94000244140625 0 0 0
0%
3Bhk 70.2300033569336 0 0 0
0%
3Bhk 74.69000244140625 0 0 0
0%
Shop 32.33000183105469 0 0 0
0%
Shop 32.61000061035156 0 0 0
0%

Wing -A

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 48.11 14 7 7
50%
2 BHK 50.52 26 12 14
46%
2 BHK 50.9 28 14 14
50%
3 BHK 70.21 28 4 24
14%
Shop 32.37 4 0 4
0%
Shop 32.64 2 0 2
0%

Wing -B

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 48.11 14 9 5
64%
2 BHK 48.17 14 9 5
64%
2 BHK 50.52 26 14 12
54%
2 BHK 50.9 14 8 6
57%
3 BHK 64.93 14 5 9
36%
3 BHK 74.72 14 5 9
36%

Construction Progress

WING -A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises4%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure46%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks48%
Stilt Floor 0%

WING -B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises4%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure46%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks48%
Stilt Floor 0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.