01
Possession Timeline
Proposed
Sep 2023
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 RK225 ft²On request
2 BHK7,833 ft²On request
1 BHK8,698 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P52000025828
Registered
2021-09-09
Litigation
No reported in source
Escrow Bank
AXIS BANK
Architect
Kishor Vithal Shinde
Total FSI
1391
04
Buildings · 1 Wing(s)
Sudarshan Heights5 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Khopoli
18.7844237,73.3498073
18.7844237,73.3498073
▸ Explore map & Street View — for verified buyers
09
Construction Progress
62% avgBasement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Plinth100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Stilt Floor 100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsStreet LightingWater Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory15
MahaRERA projects nearby in Khopoli
KHOPOLI BUSINESS CENTRE159 unitsMurlidhar Homes Phase 198 unitsGajanan Vatika Residency Building -295 unitsRIVER VIEW APARTMENTS WING C63 unitsSapphire Infra36 unitsCITY OF MUSIC PHASE IV33 unitsSWARANJALI HEIGHTS21 unitsVIMAL APARTMENT15 unitsAARTI HEIGHTS2 unitsROSE VILLAURBAN VISTA IICENTRAL PLAZA
?
Frequently Asked Questions
When is possession of Sudarshan Heights?
As per MahaRERA, proposed possession is Sep 2023.
Is Sudarshan Heights RERA-registered?
Yes — MahaRERA registration P52000025828, registered 2021-09-09. The current MahaRERA source record reports no litigations.
Who is the developer?
Sameer Dattatray Masurkar
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.