SUNSHINE SWAPNA NAGARI

by ORCHID HOUSINGINFRA LLP Partnership
Certificate Signed P51700005851
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700005851
Registration No.
REA51700010304
Registration Date
2017-08-14
Developer
ORCHID HOUSINGINFRA LLP Partnership
Architect
Pramod V Patil And Associates
Project Bank
AXIS BANK
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
2019-12-31
Units Sold
0
Buildings
10
Project Area
15300.00 sq.m
Total FSI
15221.71
Approved FSI
14616.88
MahaRERA QR
SUNSHINE SWAPNA NAGARI
MahaRERA — P51700005851
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking1
📅Completion2018-12-31
🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking1
📅Completion2018-12-31
🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking1
📅Completion2018-12-31
🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking1
📅Completion2018-12-31
🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking1
📅Completion2018-12-31
🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking1
📅Completion2018-12-31
🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking1
📅Completion2018-12-31
🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking1
📅Completion2018-12-31
🏗️Proposed Floors6
Sanctioned6
📅Completion2018-12-31
🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking1
📅Completion2018-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 27.239999771118164 0 0 0
0%
1Rk 20.010000228881836 0 0 0
0%
2Bhk 35.619998931884766 0 0 0
0%
2Bhk 36.11000061035156 0 0 0
0%
2Bhk 37.5099983215332 0 0 0
0%
2Bhk 37.75 0 0 0
0%
2Bhk 38.279998779296875 0 0 0
0%
2Bhk 38.59000015258789 0 0 0
0%
2Bhk 38.599998474121094 0 0 0
0%
Shop 8.430000305175781 0 0 0
0%
Shop 9.09000015258789 0 0 0
0%
Shop 12.369999885559082 0 0 0
0%

Sampada

Type Carpet (sq.ft) Total Booked Available Status
1RK 20.01 38 29 9
76%

Samriddhi

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 35.62 8 8 0
100%
2 BHK 37.51 8 8 0
100%
2 BHK 38.28 1 0 1
0%
2 BHK 38.6 1 0 1
0%

Sanniddhi

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 36.11 16 13 3
81%
2 BHK 37.75 16 15 1
94%
2 BHK 38.59 4 0 4
0%

Shanti

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 27.24 58 51 7
88%

Shraddha

Type Carpet (sq.ft) Total Booked Available Status
1RK 20.01 38 33 5
87%

Shubhada

Type Carpet (sq.ft) Total Booked Available Status
1RK 20.01 38 32 6
84%

Siddhi

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 27.24 39 38 1
97%

Soham

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 27.24 39 38 1
97%

Srishti

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 27.24 56 54 2
96%
SHOP 8.43 2 0 2
0%
SHOP 9.09 2 0 2
0%
SHOP 12.37 2 0 2
0%

Sukriti

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 27.24 58 49 9
84%

Construction Progress

SAMPADA

Basement (if any)100%

Sampada

Excavation100%

SAMPADA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Sampada

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SAMPADA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Sampada

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

SAMPADA

Plinth100%
Podiums (if any) 0%

Sampada

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

SAMPADA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Sampada

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SAMPADA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Sampada

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

SAMRIDDHI

Basement (if any)100%

Samriddhi

Excavation100%

SAMRIDDHI

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Samriddhi

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SAMRIDDHI

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Samriddhi

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

SAMRIDDHI

Plinth100%
Podiums (if any) 0%

Samriddhi

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

SAMRIDDHI

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Samriddhi

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SAMRIDDHI

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Samriddhi

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

SANNIDDHI

Basement (if any)100%

Sanniddhi

Excavation100%

SANNIDDHI

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Sanniddhi

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SANNIDDHI

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Sanniddhi

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

SANNIDDHI

Plinth100%
Podiums (if any) 0%

Sanniddhi

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

SANNIDDHI

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Sanniddhi

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SANNIDDHI

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Sanniddhi

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

SHANTI

Basement (if any)100%

Shanti

Excavation100%

SHANTI

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Shanti

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SHANTI

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Shanti

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

SHANTI

Plinth100%
Podiums (if any) 0%

Shanti

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

SHANTI

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Shanti

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SHANTI

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Shanti

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

SHRADDHA

Basement (if any)100%

Shraddha

Excavation100%

SHRADDHA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Shraddha

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SHRADDHA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Shraddha

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

SHRADDHA

Plinth100%
Podiums (if any) 0%

Shraddha

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

SHRADDHA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Shraddha

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SHRADDHA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Shraddha

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

SHUBHADA

Basement (if any)100%

Shubhada

Excavation100%

SHUBHADA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Shubhada

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SHUBHADA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Shubhada

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

SHUBHADA

Plinth100%
Podiums (if any) 0%

Shubhada

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

SHUBHADA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Shubhada

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SHUBHADA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Shubhada

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

SIDDHI

Basement (if any)100%

Siddhi

Excavation100%

SIDDHI

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Siddhi

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SIDDHI

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Siddhi

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

SIDDHI

Plinth100%
Podiums (if any) 0%

Siddhi

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

SIDDHI

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Siddhi

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SIDDHI

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Siddhi

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

SOHAM

Basement (if any)100%

Soham

Excavation100%

SOHAM

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Soham

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SOHAM

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Soham

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

SOHAM

Plinth100%
Podiums (if any) 0%

Soham

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

SOHAM

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Soham

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SOHAM

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Soham

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

SRISHTI

Basement (if any)100%

Srishti

Excavation100%

SRISHTI

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Srishti

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SRISHTI

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Srishti

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

SRISHTI

Plinth100%
Podiums (if any) 0%

Srishti

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

SRISHTI

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Srishti

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SRISHTI

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Srishti

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

SUKRITI

Basement (if any)100%

Sukriti

Excavation100%

SUKRITI

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Sukriti

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

SUKRITI

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Sukriti

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

SUKRITI

Plinth100%
Podiums (if any) 0%

Sukriti

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

SUKRITI

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Sukriti

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

SUKRITI

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Sukriti

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements
GYMNASIUM 100%
INDOOR GAMES ROOM 100%
Landscaping & Tree Planting 100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.