📞 +91 98200 30685✉️
RERA: A51800043517

Sunteck MaxxWorld 2, Tivri, Naigaon East

by Sunteck Realty Limited Company
Certificate SignedP99000024080

Project Information

RERA Certificate No.
P99000024080
Registration No.
REA99000068434
Registration Date
2021-09-08
Developer
Sunteck Realty Limited Company
Architect
Sandeep Shikre & Associates
Project Bank
AXIS BANK
Proposed Possession
2025-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
6259.49 sq.m
Total FSI
23552.70
Approved FSI
23552.70
MahaRERA QR
Sunteck MaxxWorld 2, Tivri, Naigaon East
MahaRERA — P99000024080
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors23
Sanctioned23
🅿️Closed Parking18
📅Completion2025-12-30
🏗️Proposed Floors24
Sanctioned24
🅿️Closed Parking18
📅Completion2025-12-30
🏗️Proposed Floors24
Sanctioned24
🅿️Closed Parking11
📅Completion2025-12-30

Apartment Configurations

Building No 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.4482802
98%
2 BHK47.0390873
97%
Retail84.13101
0%
Retail84.15101
0%
Retail94.8101
0%
Retail163.69101
0%
Retail166.96101
0%

Building No 4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.4482766
93%
2 BHK47.0390855
94%
Retail85.16202
0%
Retail164.98101
0%
Retail168.12101
0%

Building No 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.4484831
99%
2 BHK47.03908010
89%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk28.440000534057617000
0%
2Bhk47.029998779296875000
0%
Retail84.12999725341797000
0%
Retail84.1500015258789000
0%
Retail85.16000366210938000
0%
Retail94.80000305175781000
0%
Retail163.69000244140625000
0%
Retail164.97999572753906000
0%
Retail166.9600067138672000
0%
Retail168.1199951171875000
0%

Construction Progress

Building No 3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises96%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises45%
Sanitary Fittings within the flats / premises45%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Building No 4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises96%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises40%
Sanitary Fittings within the flats / premises40%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Building No 5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises94%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises94%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises40%
Sanitary Fittings within the flats / premises40%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings85%
Electrical Meter Room, Sub-Station, Receiving Station80%
Energy management
Fire Protection And Fire Safety Requirements90%
Landscaping & Tree Planting75%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal90%
Storm Water Drains98%
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Water90%
Water Conservation, Rain water Harvesting90%
Water Supply95%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now