📞 +91 98200 30685 ✉️
RERA: A51800043517

Sunteck ONEWorld 5, Tivri, Naigaon East

by Sunteck Realty Limited Company
Certificate Signed P99000033157
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P99000033157
Registration No.
REA99000102835
Registration Date
2022-02-09
Developer
Sunteck Realty Limited Company
Architect
Practice Design Pvt. Ltd
Project Bank
AXIS BANK
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
2640.00 sq.m
Total FSI
23700.00
Approved FSI
23555.15
MahaRERA QR
Sunteck ONEWorld 5, Tivri, Naigaon East
MahaRERA — P99000033157
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors24
Sanctioned24
🅿️Closed Parking3
📅Completion2026-12-31
🏗️Proposed Floors24
Sanctioned24
🅿️Closed Parking3
📅Completion2026-12-31

Apartment Configurations

Tower 10

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 28.93 83 56 27
67%
2 BHK 39.09 88 47 41
53%
Shop 25.74 1 0 1
0%
Shop 28.03 1 0 1
0%
Shop 33.91 1 0 1
0%
Shop 36.17 1 0 1
0%
Shop 36.21 1 0 1
0%
Shop 45.28 1 0 1
0%
Shop 45.71 1 0 1
0%
Shop 48.31 1 0 1
0%
Shop 52.57 1 0 1
0%
Shop 53.11 1 0 1
0%
Shop 53.32 1 0 1
0%
Shop 54.79 1 0 1
0%
Shop 56.0 1 0 1
0%
Shop 61.83 1 0 1
0%
Shop 62.37 1 0 1
0%
Shop 62.58 1 0 1
0%

Tower 9

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 28.93 83 67 16
81%
2 BHK 39.09 88 72 16
82%
Shop 25.73 2 0 2
0%
Shop 33.9 2 0 2
0%
Shop 37.98 1 0 1
0%
Shop 47.08 1 0 1
0%
Shop 59.4 1 0 1
0%
Shop 64.79 1 0 1
0%
Shop 72.24 1 0 1
0%
Shop 76.08 1 0 1
0%
Shop 119.93 2 0 2
0%

Construction Progress

Tower 10

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.16%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.1%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises18%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises3%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure96%

Tower 9

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.13%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises21%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises7%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.4%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks4%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure83%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.