Sunteck ONEWorld 3, Tivri, Naigaon East

by Sunteck Realty Limited Company
Certificate SignedP99000033099

Project Information

RERA Certificate No.
P99000033099
Registration No.
REA99000102759
Registration Date
2022-02-09
Developer
Sunteck Realty Limited Company
Architect
Practice Design Pvt. Ltd
Project Bank
AXIS BANK
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
2955.00 sq.m
Total FSI
23500.00
Approved FSI
23375.86
MahaRERA QR
Sunteck ONEWorld 3, Tivri, Naigaon East
MahaRERA — P99000033099
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors24
Sanctioned24
🅿️Closed Parking3
📅Completion2026-12-31
🏗️Proposed Floors24
Sanctioned24
🅿️Closed Parking3
📅Completion2026-12-31

Apartment Configurations

Tower 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.9383083
0%
2 BHK39.0988088
0%
Shop25.42101
0%
Shop28.03101
0%
Shop33.59101
0%
Shop35.93101
0%
Shop36.17101
0%
Shop45.28101
0%
Shop46.12101
0%
Shop49.55101
0%
Shop50.37101
0%
Shop51.14101
0%
Shop51.15101
0%
Shop55.67101
0%
Shop59.45101
0%
Shop61.49101
0%
Shop62.27202
0%

Tower 6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.93836518
78%
2 BHK39.09883256
36%
Shop25.74101
0%
Shop28.04101
0%
Shop33.91101
0%
Shop36.21101
0%
Shop36.3101
0%
Shop45.41101
0%
Shop65.24101
0%
Shop72.7101
0%
Shop120.19101
0%

Construction Progress

Tower 5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure4%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

Tower 6

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure4%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure4%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now