The White Villas

by St. Angelo's Vnct Ventures Pvt. Ltd. Company
Certificate SignedP51700000038
The White VillasProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700000038
Registration No.
REA51700001626
Registration Date
2021-03-02
Developer
St. Angelo's Vnct Ventures Pvt. Ltd. Company
Architect
TANGENT ARCHITECT
Project Bank
STATE BANK OF INDIA
Proposed Possession
2027-04-30
Total Units
43
Units Sold
33 (77%)
Buildings
43
Project Area
8000.00 sq.m
Total FSI
7200.00
Approved FSI
7200.00
MahaRERA QR
The White Villas
MahaRERA โ€” P51700000038
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1

Apartment Configurations

APHRODITE VILLA NO 3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

APOLLO VILLA NO 4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

ARTEMIS VILLA NO 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22101
0%

ASTRAEA VILLA NO 6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22101
0%

ATHENA VILLA NO 7

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22101
0%

ATLANTIS VILLA NO 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

ATLAS VILLA NO 8

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22101
0%

ATTIS VILLA NO 9

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22101
0%

BIA VILLA NO 10

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22101
0%

CASTOR VILLA NO 11

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2BHK71.93110
100%

CERUS VILLA NO 12

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

CLIO VILLA NO 14

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

CRONUS VILLA NO 15

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

CYBELE VILLA NO 16

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

DEMETER VILLA NO 17

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

ELECTRA VILLA NO 18

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

EOS VILLA NO 19

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

ERATO VILLA NO 20

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

EROS VILLA NO 21

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

GAIA VILLA NO 22

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

HARMONIA VILLA NO 23

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

HELIOS VILLA NO 25

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

HEMERA VILLA NO 26

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

HERA VILLA NO 27

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

HERMES VILLA NO 29

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

HESPERUS VILLA NO 30

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

IRIS VILLA NO 33

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

KETO VILLA NO 13

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

KRATOS VILLA NO 34

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

MAIA VILLA NO 35

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

METIS VILLA NO 36

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22101
0%

NYX VILLA NO 38

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22101
0%

OCEANUS VILLA NO 39

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.02110
100%

PHEME VILLA NO 40

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK80.29110
100%

PLUTUS VILLA NO 41

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

RHEA VILLA NO 42

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK86.53110
100%

SELENE VILLA NO 43

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2BHK64.71110
100%

STYX VILLA NO 44

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2BHK79.85110
100%

THALIA VILLA NO 37

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22101
0%

TRITON VILLA NO 31

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

URANIA VILLA NO 28

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22101
0%

ZEPHYR VILLA NO 24

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

ZEUS VILLA NO 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK87.22110
100%

Construction Progress

APHRODITE VILLA NO 3

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

APOLLO VILLA NO 4

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

ARTEMIS VILLA NO 5

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

ASTRAEA VILLA NO 6

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

ATHENA VILLA NO 7

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

ATLANTIS VILLA NO 2

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

ATLAS VILLA NO 8

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

ATTIS VILLA NO 9

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

BIA VILLA NO 10

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

CASTOR VILLA NO 11

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

CERUS VILLA NO 12

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

CLIO VILLA NO 14

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

CRONUS VILLA NO 15

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

CYBELE VILLA NO 16

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

DEMETER VILLA NO 17

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

ELECTRA VILLA NO 18

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

EOS VILLA NO 19

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

ERATO VILLA NO 20

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

EROS VILLA NO 21

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

GAIA VILLA NO 22

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor80%

HARMONIA VILLA NO 23

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

HELIOS VILLA NO 25

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

HEMERA VILLA NO 26

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

HERA VILLA NO 27

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

HERMES VILLA NO 29

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.200%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

HESPERUS VILLA NO 30

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

IRIS VILLA NO 33

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

KETO VILLA NO 13

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

KRATOS VILLA NO 34

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

MAIA VILLA NO 35

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

METIS VILLA NO 36

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

NYX VILLA NO 38

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

OCEANUS VILLA NO 39

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

PHEME VILLA NO 40

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

PLUTUS VILLA NO 41

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

RHEA VILLA NO 42

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

SELENE VILLA NO 43

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

STYX VILLA NO 44

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

THALIA VILLA NO 37

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

TRITON VILLA NO 31

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

URANIA VILLA NO 28

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

ZEPHYR VILLA NO 24

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor80%

ZEUS VILLA NO 1

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor80%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โœ…Community Buildings
โœ…Electrical meter room, sub-station, receiving station100%
โœ…Energy managemcnt100%
โฌœFire protection and fire safety requirements
โœ…Internal Roads & Footpaths50%
โœ…Landscaping & Tree Planting100%
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
โœ…Solid Waste Management And Disposal50%
โœ…Storm Water Drains100%
โœ…Street Lighting100%
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply100%
โœ…Water conservation /Rain water harvesting