List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Unique Vistas Mhada Building No. 1,2,3

by Madhu Harshad Doshi Individual
Certificate SignedP51700006925
Want us to WhatsApp you? Enter your mobile — we’ll say hello and take it from there.
+91

Project Information

RERA Certificate No.
P51700006925
Registration No.
REA51700012079
Registration Date
2021-09-10
Developer
Madhu Harshad Doshi Individual
Architect
10 FOLDS ARCHITECTS & CONSULTANTS
Project Bank
AXIS BANK
Proposed Possession
2026-09-30
Revised Possession
2022-06-30
Extended Possession
2023-12-31
Total Units
508
Units Sold
0 (0%)
Buildings
3
Project Area
1069.15 sq.m
Total FSI
16325.48
Approved FSI
16325.48
Litigations
โš ๏ธ Yes
MahaRERA QR
Unique Vistas Mhada Building No. 1,2,3
MahaRERA โ€” P51700006925
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors31
โœ…Sanctioned31
๐Ÿ Habitable31
๐Ÿ”ขTotal Units178
๐ŸกResidential178
๐Ÿ—๏ธProposed Floors31
โœ…Sanctioned31
๐Ÿ Habitable31
๐Ÿ”ขTotal Units149
๐ŸกResidential145
๐ŸขNon-Residential4
๐Ÿ—๏ธProposed Floors31
โœ…Sanctioned31
๐Ÿ Habitable31
๐Ÿ”ขTotal Units181
๐ŸกResidential176
๐ŸขNon-Residential5

Apartment Configurations

Bldg -1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.161061
0%
1 BHK29.2955055
0%
1 BHK29.3162062
0%

Bldg -3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.741150115
0%
1 BHK30.5930030
0%
Shop12.88101
0%
Shop16.19101
0%
Shop19.03101
0%
Shop38.13101
0%

Bldg-2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.160060
0%
1 BHK29.291160116
0%
Shop16.19202
0%
Shop28.21303
0%

Construction Progress

BLDG -1

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises90%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BLDG -3

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises90%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BLDG-2

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises90%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space100%
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station70%
โœ…Energy managemcnt85%
โœ…Fire protection and fire safety requirements100%
โœ…Internal Roads & Footpaths
โœ…Landscaping & Tree Planting100%
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
โœ…Solid Waste Management And Disposal100%
โœ…Storm Water Drains100%
โœ…Street Lighting100%
โœ…Treatment And Disposal Of Sewage And Sullage Water100%
โœ…Water Supply
โœ…Water conservation /Rain water harvesting100%

Latest Mumbai Property News

View all news โ†’
CallWhatsApp
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now