UNIQUE VISTAS MHADA BUILDING NO. 1,2,3

by MADHU HARSHAD DOSHI Individual
Certificate Signed P51700006925
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700006925
Registration No.
REA51700012079
Registration Date
2021-09-10
Developer
MADHU HARSHAD DOSHI Individual
Architect
Ten Folds
Project Bank
AXIS BANK
Proposed Possession
2022-06-30
Revised Possession
2022-06-30
Extended Possession
2023-12-31
Units Sold
0
Buildings
3
Project Area
1069.15 sq.m
Total FSI
16325.48
Approved FSI
16325.48
MahaRERA QR
UNIQUE VISTAS MHADA BUILDING NO. 1,2,3
MahaRERA — P51700006925
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors31
Sanctioned31
🏠Habitable30
📅Completion2022-06-30
🏗️Proposed Floors31
Sanctioned31
🏠Habitable30
🅿️Closed Parking1
📅Completion2022-06-30
🏗️Proposed Floors31
Sanctioned31
🏠Habitable30
🅿️Closed Parking1
📅Completion2022-06-30

Apartment Configurations

Bldg -1

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.1 61 0 61
0%
1 BHK 29.29 55 0 55
0%
1 BHK 29.31 62 0 62
0%

Bldg -3

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 28.74 115 0 115
0%
1 BHK 30.59 30 0 30
0%
Shop 12.88 1 0 1
0%
Shop 16.19 1 0 1
0%
Shop 19.03 1 0 1
0%
Shop 38.13 1 0 1
0%

Bldg-2

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.1 60 0 60
0%
1 BHK 29.29 116 0 116
0%
Shop 16.19 2 0 2
0%
Shop 28.21 3 0 3
0%

Construction Progress

BLDG -1

Basement (if any)100%

Bldg -1

Excavation100%

BLDG -1

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Bldg -1

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80%

BLDG -1

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Bldg -1

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing85%

BLDG -1

Plinth100%
Podiums (if any) 0%

Bldg -1

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises70%

BLDG -1

Sanitary Fittings within the flats / premises70%
Slabs of Super Structure100%

Bldg -1

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BLDG -1

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Bldg -1

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BLDG -3

Basement (if any)100%

Bldg -3

Excavation100%

BLDG -3

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Bldg -3

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%

BLDG -3

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Bldg -3

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing79%

BLDG -3

Plinth100%
Podiums (if any) 0%

Bldg -3

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises40%

BLDG -3

Sanitary Fittings within the flats / premises70%
Slabs of Super Structure100%

Bldg -3

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BLDG -3

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Bldg -3

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BLDG-2

Basement (if any)100%

Bldg-2

Excavation100%

BLDG-2

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Bldg-2

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%

BLDG-2

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Bldg-2

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing79%

BLDG-2

Plinth100%
Podiums (if any) 0%

Bldg-2

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises40%

BLDG-2

Sanitary Fittings within the flats / premises70%
Slabs of Super Structure100%

Bldg-2

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BLDG-2

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Bldg-2

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 60%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 40%
Energy management
Fire Protection And Fire Safety Requirements 70%
Landscaping & Tree Planting 50%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 80%
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 100%
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.