VAISHNAVI RESIDENCY

by Vaishnavi Developers
Certificate SignedPR1240002501566
VAISHNAVI RESIDENCYProject photos will appear here when available.

Project Information

RERA Certificate No.
PR1240002501566
Developer
Vaishnavi Developers
Proposed Possession
2030-12-31
Total Units
25
Units Sold
0 (0%)
Buildings
4
MahaRERA QR
VAISHNAVI RESIDENCY
MahaRERA โ€” PR1240002501566
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ Habitable5
๐Ÿ”ขTotal Units22
๐ŸกResidential16
๐ŸขNon-Residential6
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1
๐Ÿ—๏ธProposed Floors2
โœ…Sanctioned2
๐Ÿ Habitable2
๐Ÿ”ขTotal Units1
๐ŸกResidential1

Construction Progress

Building 1

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
Stilt Floor100%

Building 2A

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor25%

Building 2B

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor25%

Building 2C

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor25%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โฌœEnergy managemcnt
โฌœFire protection and fire safety requirements
โœ…Internal Roads & Footpaths10%
โœ…Landscaping & Tree Planting10%
โœ…Open Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)15%
โฌœSolid Waste Management And Disposal
โœ…Storm Water Drains10%
โœ…Street Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply10%
โฌœWater conservation /Rain water harvesting