102
Units
2022
Possession
5
Buildings
Kept in Abeyance
Status
01Possession Timeline
Proposed
Dec 2022
Revised
Dec 2024
Status
On-Going Project
⚠ Possession revised later than originally proposed β€” per MahaRERA.
02Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 RK232–271 ftΒ²On request
1 BHK367–408 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03RERA Trust Record
MahaRERA No.
P51700003380
Registered
β€”
Litigation
None on record
Escrow Bank
BANK OF BARODA
Architect
Dilip Navratanji Mehta
Total FSI
9040
04Buildings Β· 5 Wing(s)
A1β€” floors Β· β€” units
A2β€” floors Β· β€” units
A3β€” floors Β· β€” units
Bβ€” floors Β· β€” units
Cβ€” floors Β· β€” units
05Land DNA Β· Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06Location
πŸ“ Karav Village
19.117363576757830,73.316680023956220
β–Έ Explore map & Street View β€” for verified buyers
09Construction Progress60% avg
Excavation100%
Stilt Floor100%
X number of Basement(s) and Plinth100%
X number of Slabs of Super Structure100%
Excavation80%
Excavation70%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.60%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises40%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing35%
Overall Percentage of Completion of the work done For the entire Building /Wing33%
X number of Slabs of Super Structure30%
Overall Percentage of Completion of the work done For the entire Building /Wing20%
Overall Percentage of Completion of the work done For the entire Building /Wing8%
10Amenities
Aggregate area of recreational Open SpaceCommunity BuildingsENTRY GATELandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater Supply
12Floor Plans, E-Brochure & Payment Plans
πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13EMI Calculator
β€”
?Frequently Asked Questions
When is possession of Vangani Darshan Phase 1?

As per MahaRERA, proposed possession is Dec 2022, revised to Dec 2024.

Is Vangani Darshan Phase 1 RERA-registered?

Yes β€” MahaRERA registration P51700003380. No litigations on record.

Who is the developer?

Panika Infrastructures Pvt. Ltd. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Karav Village β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
βœ“ MahaRERA P51700077356β˜… Featured
Lodha Group
Lodha Hanging Gardens, Dombivali
3 BHK, 4 BHK Β· β‚Ή16,400/sq.ft Β· Possession Dec 2027
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’