01
Possession Timeline
Proposed
Dec 2019
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop89–167 ft²On request
1 RK191–223 ft²On request
1 BHK341–366 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P99000015763
Registered
2018-03-22
Litigation
No reported in source
Escrow Bank
BHARAT COOPERATIVE BANK MUMBAI LIMITED
Architect
En Con
Total FSI
2383
04
Buildings · 2 Wing(s)
Varun - P9 floors · — units
Varun - Q9 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Village Sativali
19.373481999999999,72.886993000000004
19.373481999999999,72.886993000000004
▸ Explore map & Street View — for verified buyers
09
Construction Progress
31% avgBasement (if any)100%
Excavation100%
Plinth100%
X number of Basement(s) and Plinth100%
Slabs of Super Structure15%
X number of Slabs of Super Structure15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
10
Amenities
Community BuildingsElectrical Meter Room, Sub-Station, Receiving StationEnergy managementFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Village Sativali
Residential · Sale
₹10,000–45,000/sqft
Commercial · Sale
₹6,500–15,000/sqft
2 BHK · Rent
₹20,000–45,000/mo
Full rates
15
MahaRERA projects nearby in Village Sativali
?
Frequently Asked Questions
When is possession of Varun Buildcon?
As per MahaRERA, proposed possession is Dec 2019.
Is Varun Buildcon RERA-registered?
Yes — MahaRERA registration P99000015763, registered 2018-03-22. The current MahaRERA source record reports no litigations.
Who is the developer?
Deepak Bhupatrai Vora — 2 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.