Project Information

RERA Certificate No.
P51700006197
Registration No.
REA51700012114
Registration Date
2017-08-14
Developer
MOHAN HARDASMAL THARWANI Individual
Architect
Raj Associate
Project Bank
PUNJAB NATIONAL BANK
Proposed Possession
2019-11-30
Revised Possession
2019-11-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
4098.50 sq.m
Total FSI
5935.16
Approved FSI
5935.16
MahaRERA QR
vedant imperial ABC phase 1
MahaRERA — P51700006197
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors14
Sanctioned14
🚗Open Parking2
🅿️Closed Parking10
📅Completion2019-11-30
🏗️Proposed Floors14
Sanctioned14
🚗Open Parking2
🅿️Closed Parking14
📅Completion2019-11-30
🏗️Proposed Floors13
Sanctioned13
🚗Open Parking2
🅿️Closed Parking10
📅Completion2019-11-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk 29.459999084472656 0 0 0
0%
1Bhk 27.239999771118164 0 0 0
0%
1Rk 17.5 0 0 0
0%
1Rk 18.299999237060547 0 0 0
0%
2 Bhk 40.83000183105469 0 0 0
0%

Wing A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.46 47 38 9
81%
1RK 18.3 1 0 1
0%

Wing B

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 27.24 1 0 1
0%
2 BHK 40.83 47 45 2
96%

Wing C

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.46 21 6 15
29%
1RK 17.5 1 0 1
0%
2 BHK 40.83 22 20 2
91%

Construction Progress

WING A

Basement (if any)100%

Wing A

Excavation100%

WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%

WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%

Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%
Overall Percentage of Completion of the work done For the entire Building /Wing79%

WING A

Plinth100%
Podiums (if any) 0%

Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

WING A

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING B

Basement (if any)100%

Wing B

Excavation100%

WING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%

WING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%

Wing B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%
Overall Percentage of Completion of the work done For the entire Building /Wing79%

WING B

Plinth100%
Podiums (if any) 0%

Wing B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

WING B

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Wing B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING C

Basement (if any)100%

Wing C

Excavation100%

WING C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%

Wing C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate30%

WING C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%

Wing C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70%
Overall Percentage of Completion of the work done For the entire Building /Wing71%

WING C

Plinth100%
Podiums (if any) 0%

Wing C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

WING C

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Wing C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing C

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing60%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 100%
Water Supply 80%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.