Western Park

by Western Real Estate Pvt. Ltd.
Certificate SignedP51700004620
Western ParkProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700004620
Registration No.
REA51700011291
Registration Date
2020-06-13
Developer
Western Real Estate Pvt. Ltd.
Architect
Avinash D Mhatre
Project Bank
HDFC BANK
Proposed Possession
2028-07-31
Revised Possession
2020-10-30
Extended Possession
2025-03-30
Units Sold
0
Buildings
2
Project Area
2655.00 sq.m
Total FSI
16956.78
Approved FSI
15269.08
MahaRERA QR
Western Park
MahaRERA โ€” P51700004620
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors12
โœ…Sanctioned12
๐Ÿ—๏ธProposed Floors12
โœ…Sanctioned12

Apartment Configurations

AL- FAROOQUE APARTMENT

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK36.5179709
89%
1BHK38.2777743
96%
Shop13.54853
62%
Shop17.17862
75%
Shop18.12844
50%

AL- SIDDIQUE APARTMENT

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK36.51908010
89%
1BHK38.27948410
89%
Shop13.541129
18%
Shop17.1711110
9%
Shop18.12909
0%

Construction Progress

AL- FAROOQUE APARTMENT

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

AL- SIDDIQUE APARTMENT

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station100%
โœ…Energy managemcnt
โœ…Fire protection and fire safety requirements100%
โœ…Internal Roads & Footpaths100%
โœ…Landscaping & Tree Planting90%
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
โœ…Solid Waste Management And Disposal100%
โœ…Storm Water Drains
โœ…Street Lighting90%
โฌœTreatment And Disposal Of Sewage And Sullage Water
โฌœWater Supply
โœ…Water conservation /Rain water harvesting100%