Yashraj Tower by Rutuja Developers

Rutuja Developers
πŸ“ Aurangabad Β· 431003
β€”
Units
2018
Possession
1
Buildings
RERA
Status
01

Possession Timeline

Proposed
Nov 2018
Revised
Oct 2023
Status
Ongoing
⚠ Possession revised later than originally proposed β€” per MahaRERA.
02

Unit Configurations (per MahaRERA)

03

RERA Trust Record

MahaRERA No.
P51500005659
Registered
β€”
Litigation
None on record
Escrow Bank
THE COSMOS CO OPERATIVE BANK LIMITED
Architect
DHANJAJ DOIFODE
Total FSI
β€”
04

Buildings Β· 1 Wing(s)

YASHRAJ TOWER6 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Aurangabad
18.148526400000000,73.977504700000000
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

Raju Prabhu KakdePartner
09

Construction Progress

86% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Stilt Floor 100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
Podiums (if any) 0%
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
?

Frequently Asked Questions

When is possession of Yashraj Tower?

As per MahaRERA, proposed possession is Nov 2018, revised to Oct 2023.

Is Yashraj Tower RERA-registered?

Yes β€” MahaRERA registration P51500005659. No litigations on record.

Who is the developer?

Rutuja Developers

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Aurangabad β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P51900079270β˜… Featured
Runwal Enterprises
7 Mahalaxmi, Mahalaxmi
2 BHK, 3 BHK, 4 BHK Β· β‚Ή56,000/sq.ft Β· Possession Dec 2031
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’