YOGI NIWAS

by ELITE INFRASTRUCTURE Partnership
Certificate Signed P51700002560
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700002560
Registration No.
REA51700005897
Registration Date
2017-08-01
Developer
ELITE INFRASTRUCTURE Partnership
Architect
Jitendra S Patel Samarthya Engineers
Project Bank
IDBI BANK
Proposed Possession
2018-06-30
Revised Possession
2018-06-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
12985.51 sq.m
Total FSI
18493.37
Approved FSI
10696.91
MahaRERA QR
YOGI NIWAS
MahaRERA — P51700002560
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors13
Sanctioned13
📅Completion2018-06-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 28.270000457763672 0 0 0
0%
1Bhk 30.020000457763672 0 0 0
0%
1Bhk 30.18000030517578 0 0 0
0%
1Bhk 31.020000457763672 0 0 0
0%
1Bhk 31.850000381469727 0 0 0
0%
2Bhk 36.63999938964844 0 0 0
0%
2Bhk 37.61000061035156 0 0 0
0%

Building No 9

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 28.27 1 1 0
100%
1 BHK 30.02 12 12 0
100%
1 BHK 30.18 2 2 0
100%
1 BHK 31.02 12 12 0
100%
1 BHK 31.85 23 22 1
96%
2 BHK 36.64 48 44 4
92%
2 BHK 37.61 4 4 0
100%

Construction Progress

BUILDING NO 9

Basement (if any)100%

Building No 9

Excavation100%

BUILDING NO 9

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%

Building No 9

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate25%

BUILDING NO 9

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%

Building No 9

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%

BUILDING NO 9

Plinth100%
Podiums (if any) 0%

Building No 9

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 9

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Building No 9

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%

BUILDING NO 9

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%

Building No 9

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 30%
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 50%
Energy management 50%
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking 50%
Sewerage (Chamber, Lines, Septic Tank , STP) 50%
Solid Waste Management And Disposal
Storm Water Drains 50%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 50%
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.