Thanekar Palacio Phase II

📍 Badlapur East, Thane · 421503
257
Units
2026
Possession
7
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2026
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
1 BHK338–366 ft²₹25 L–₹27 L
2 BHK500–558 ft²₹36 L–₹41 L
3 BHK646–758 ft²₹47 L–₹55 L
Shop190–1,013 ft²₹14 L–₹74 L
Bungalow1,003–1,250 ft²₹73 L–₹91 L
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Live availability, floor plans & today's price — on WhatsApp
03

RERA Trust Record

MahaRERA No.
P51700051381
Registered
2024-03-02
Litigation
None on record
Escrow Bank
STATE BANK OF INDIA
Architect
Suraj
Total FSI
18251
04

Buildings · 7 Wing(s)

Bunglow Type A1 floors · — units
Bunglow Type B1 floors · — units
Bunglow Type C1 floors · — units
Bunglow Type D1 floors · — units
Bunglow Type E— floors · — units
Bunglow Type F— floors · — units
Thanekar Palacio Phase Ii19 floors · — units
05

Land DNA · Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06

Location

📍 Badlapur East
19.218330700000000,72.978089700000000
▸ Explore map & Street View — for verified buyers
07

Promoter & Professionals

Thanekar Construction LLPNA
Advait Ajay ThanekarPartner
Ajay Madhukar ThanekarPartner
Arya Ajay Thanekar Partner
SURAJ ANDHAREArchitect
Vaishali Ajay ThanekarPartner
08

Availability & Pricing

TypeCarpetPriceAvail
2 BHK650 ft²₹48 Lac
3 BHK1100 ft²₹60 Lac
09

Construction Progress

88% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
10

Amenities

Kids Play AreaGardenClubhouseIndoor GamesMultipurpose HallGymnasiumJogging TrackYoga RoomCCTV24x7 SecurityVideo Door PhoneFire SafetyIntercomPower BackupParkingVisitor ParkingConcealed WiringConcealed Plumbing
12

Floor Plans, E-Brochure & Payment Plans

📐 Unit floor plans📄 Official e-brochure💳 Payment plans · 20:80 · subvention · current offers

Shared on WhatsApp by our MahaRERA advisor — including the latest builder offers and payment schemes we don't list publicly.

💬 Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

14

More by Thanekar Construction

Thanekar PalacioBadlapur · Sold OutThanekar CivicBadlapur · Sold OutThanekar ParadiseBadlapur · Sold Out
15

MahaRERA projects nearby in Badlapur East

Pradhan Mantri Awas Yojana - Urban2352 unitsTulsi Aanand320 unitsPark One, Phase I220 unitsEkdant Pooja Chsl147 unitsNano City115 unitsSai Matoshree108 unitsKartik Homes104 unitsVrindavan Residency85 unitsPark One Phase Ii83 unitsGrand Unity Residences74 unitsPlatinum Willows65 unitsKulswamini58 units
?

Frequently Asked Questions

When is possession of Thanekar Palacio Phase Ii?

As per MahaRERA, proposed possession is Dec 2026.

Is Thanekar Palacio Phase Ii RERA-registered?

Yes — MahaRERA registration P51700051381, registered 2024-03-02. No litigations on record.

What configurations and prices are available?

2 configuration(s), including 2 BHK of 650 sqft at ₹48 Lac. See the pricing table above.

Who is the developer?

Thanekar Construction — 6 projects tracked on Mumbai Property Exchange. View their track record ▸

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.

SOURCE · MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA · RERA A51800043517 · EST. 1995
WhatsAppEnquire ▸
🎯 AI Matchmaker
Tell us what you want in Badlapur East — get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
✓ MahaRERA P52000016540★ Featured
The Wadhwa Group
Wadhwa Wise City, New Panvel
1 BHK, 2 BHK, 3 BHK · ₹16,946/sq.ft · Possession 2026-12-01 00:00:00
Learn more ›

📰 Latest Mumbai Property News

View all news →