📞 +91 98200 30685 ✉️
RERA: A51800043517

Arkade Rise

by Arkade Paradigm Partnership
Certificate Signed P51900015795
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51900015795
Registration No.
REA51900033906
Registration Date
2021-09-10
Developer
Arkade Paradigm Partnership
Architect
Kalakruti Architects & Planners
Project Bank
BANK OF BARODA
Proposed Possession
2021-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
453.42 sq.m
Total FSI
1842.62
Approved FSI
1842.62
MahaRERA QR
Arkade Rise
MahaRERA — P51900015795
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors28
Sanctioned28
⬇️Basements1
📅Completion2020-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2 Bhk 109.80999755859375 0 0 0
0%
3 Bhk 143.00999450683594 0 0 0
0%

Arkade Rise

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 109.81 2 2 0
100%
3 BHK 143.01 10 6 4
60%

Construction Progress

Arkade Rise

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate6%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.6%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises4%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises4%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure70%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.24%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks24%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure70%

RERA Registered Amenities

Aggregate area of recreational Open Space
BASEMENT 80%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
FITNESS CENTER SOCIETY 50%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 80%
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.