✓ MahaRERA P52000027236RERA: no litigation reported168
Units
2024
Possession
3
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Jun 2024
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 BHK347–431 ft²On request
2 BHK503–700 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P52000027236
Registered
2021-09-08
Litigation
No reported in source
Escrow Bank
BANK OF INDIA
Architect
Rajesh Rc
Total FSI
5565
04
Buildings · 3 Wing(s)
Building 5Type C8 floors · — units
Building 6 Type D8 floors · — units
Building 7 Type E8 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Rees Khalapur
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
Deepak Valji KariaPartner
Dharmendra Valji KariaPartner
Harnish Dharmendra KariaPartner
Nakshata ShahPartner
Yash Deepak KariaPartner
09
Construction Progress
82% avgBasement (if any)100%
Plinth100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Slabs of Super Structure95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
Excavation0%
Podiums (if any) 0%
10
Amenities
Aggregate area of recreational Open SpaceClub HouseElectrical Meter Room, Sub-Station, Receiving StationLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsStreet LightingWater Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory14
More by Choice Buildcon
15
MahaRERA projects nearby in Rees Khalapur
?
Frequently Asked Questions
When is possession of Choice Ambe Smruti?
As per MahaRERA, proposed possession is Jun 2024.
Is Choice Ambe Smruti RERA-registered?
Yes — MahaRERA registration P52000027236, registered 2021-09-08. The current MahaRERA source record reports no litigations.
Who is the developer?
Choice Buildcon — 4 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.