List PropertyWhatsApp
New ProjectsBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your PropertyπŸ’¬ WhatsApp Us
🏠 Mumbai property advisory & dataOperating since 1995βœ“ MahaRERA A51800043517βœ“ RERA-verified project data🟒 We reply in minutes on WhatsApp
D
βœ“ MahaRERA P99000054789βœ“ Clear

Dhananjay And Hayaat Industrial Estate by M M Infra Project

M M Infra Project
πŸ“ Waliv, Palghar Β· 401208
45
Units
2028
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2028
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
Shop373–1,639 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P99000054789
Registered
2024-02-12
Litigation
None on record
Escrow Bank
FEDERAL BANK
Architect
Vipul Adhia
Total FSI
4500
04

Buildings Β· 1 Wing(s)

Building No 33 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Waliv
19.429619000000000,72.875924000000000
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

Mahibullah Mohammad Shafi KhanPartner
Munir Ahmed Mohammad Saeed KhanPartner
SANJARALI H CHOUDHARIPartner
USMAN AHMAD KHANPartner
09

Construction Progress

14% avg
Excavation100%
Basement (if any)30%
Plinth30%
X number of Basement(s) and Plinth30%
Overall Percentage of Completion of the work done For the entire Building /Wing13%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
10

Amenities

Electrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
14

More by M M Infra Project

Embassy SerenityAlibaug Β· Under ConstructionEmaar Casa VeneroAlibaug Β· Under ConstructionMahindra MeridianAlibaug Β· Under ConstructionHiranandani SandsAlibaug Β· Under ConstructionJVM OdysseusThane West Β· Under ConstructionJVM CynergyThane East Β· Under Construction
15

MahaRERA projects nearby in Waliv

APEKSHA COMPLEX208 unitsGovind Enclave119 unitsASHIYANA118 unitsCHAITANYA SIGNATURE73 unitsSHASHWAT AANGAN Building / Wing A and CBASERA GARDENAtharva ClassicAQSA BUILDING 2Hayaat Galaxy IISPACE HEIGHTS - PHASE 2POONAM IMPERIA PHASE IISAPPHIRE INDUSTRIAL PREMISES
?

Frequently Asked Questions

When is possession of DHANANJAY AND HAYAAT INDUSTRIAL ESTATE?

As per MahaRERA, proposed possession is Dec 2028.

Is DHANANJAY AND HAYAAT INDUSTRIAL ESTATE RERA-registered?

Yes β€” MahaRERA registration P99000054789, registered 2024-02-12. No litigations on record.

Who is the developer?

M M Infra Project β€” 2688 projects tracked on Mumbai Property Exchange.

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Waliv β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P51900079270β˜… Featured
Runwal Enterprises
7 Mahalaxmi, Mahalaxmi
2 BHK, 3 BHK, 4 BHK Β· β‚Ή56,000/sq.ft Β· Possession Dec 2031
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’