Project Information

RERA Certificate No.
P51800003604
Registration No.
REA51800008419
Registration Date
2017-08-05
Developer
Dev Land & Housing Pvt Ltd Company
Architect
Om Associates
Project Bank
PUNJAB NATIONAL BANK
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1096.15 sq.m
Total FSI
2192.26
Approved FSI
2192.26
MahaRERA QR
Dlh Ornate
MahaRERA — P51800003604
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors20
Sanctioned20
⬇️Basements1
🅿️Closed Parking1
📅Completion1900-01-01

Apartment Configurations

Dlh Ornate

TypeCarpet (sq.ft)TotalBookedAvailableStatus
4 BHK156.311110
100%
6 BHK266.75110
100%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
4Bhk156.3000030517578000
0%
6Bhk266.75000
0%

Construction Progress

DLH ORNATE

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%

Dlh Ornate

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate85%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%
Overall Percentage of Completion of the work done For the entire Building /Wing82%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure80%

RERA Registered Amenities

Aggregate area of recreational Open Space100%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management
Fire Protection And Fire Safety Requirements80%
Landscaping & Tree Planting100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal100%
Storm Water Drains100%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting100%
Water Supply80%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.