Project Information

RERA Certificate No.
P51900000138
Registration No.
REA51900002809
Registration Date
2019-04-26
Developer
Nahar Excalibur Project Private Limited Company
Architect
Mr. Ketan Vaidya
Project Bank
ICICI BANK LIMITED
Proposed Possession
2019-06-30
Revised Possession
2019-06-30
Extended Possession
2020-12-30
Units Sold
0
Buildings
3
Project Area
2503.36 sq.m
Total FSI
12835.52
Approved FSI
11430.21
MahaRERA QR
Excalibur By Nahar
MahaRERA — P51900000138
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors25
Sanctioned25
⬇️Basements1
🚗Open Parking5
🅿️Closed Parking24
📅Completion1900-01-01
🏗️Proposed Floors27
Sanctioned27
⬇️Basements1
🅿️Closed Parking58
📅Completion2019-06-30
🏗️Proposed Floors25
Sanctioned25
⬇️Basements1
🅿️Closed Parking35
📅Completion1900-01-01

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
3Bhk 133.13999938964844 0 0 0
0%
Rehabresidential1bhk 39.099998474121094 0 0 0
0%
Rehabresidential1bhk 40.16999816894531 0 0 0
0%
Rehabresidential1bhk 42.66999816894531 0 0 0
0%
Rehbresidential1bhk 40.16999816894531 0 0 0
0%
Residential3bhk 162.75999450683594 0 0 0
0%
Residential5bhk 234.44000244140625 0 0 0
0%
Residential5bhk 267.3699951171875 0 0 0
0%
Residential5bhk 279.45001220703125 0 0 0
0%

Ayeshabai

Type Carpet (sq.ft) Total Booked Available Status
REHABRESIDENTIAL1 BHK 40.17 80 80 0
100%
REHABRESIDENTIAL1 BHK 42.67 12 12 0
100%

Excalibur By Nahar

Type Carpet (sq.ft) Total Booked Available Status
3 BHK 133.14 28 16 12
57%
RESIDENTIAL3 BHK 162.76 3 3 0
100%
RESIDENTIAL5 BHK 234.44 1 1 0
100%
RESIDENTIAL5 BHK 267.37 1 1 0
100%
RESIDENTIAL5 BHK 279.45 1 1 0
100%

Haji Gul Mohammad

Type Carpet (sq.ft) Total Booked Available Status
REHABRESIDENTIAL1 BHK 39.1 20 20 0
100%
REHBRESIDENTIAL1 BHK 40.17 92 92 0
100%

Construction Progress

Ayeshabai

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

EXCALIBUR BY NAHAR

Basement (if any)100%

Excalibur By Nahar

Excavation100%

EXCALIBUR BY NAHAR

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Excalibur By Nahar

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

EXCALIBUR BY NAHAR

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Excalibur By Nahar

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

EXCALIBUR BY NAHAR

Plinth100%
Podiums (if any) 100%

Excalibur By Nahar

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises97%

EXCALIBUR BY NAHAR

Sanitary Fittings within the flats / premises97%
Slabs of Super Structure100%

Excalibur By Nahar

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

EXCALIBUR BY NAHAR

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Excalibur By Nahar

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

Haji Gul Mohammad

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 95%
Energy management
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.