List PropertyWhatsApp
New ProjectsBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property💬 WhatsApp Us
🏆 Mumbai's oldest property portalSince 1995✓ MahaRERA A51800043517✓ RERA-verified project data🟢 We reply in minutes on WhatsApp
G
✓ MahaRERA P52000017468✓ Clear

Green Park Phase - II by Shreeji Associates

📍 Mahad, Raigarh · 402301
126
Units
2024
Possession
5
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2024
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
Flat No G 704236 ft²On request
Flat No G 204241 ft²On request
Flat No G 304241 ft²On request
Flat No G 404241 ft²On request
Flat No G 104241 ft²On request
Flat No G 504241 ft²On request
Flat No G 604241 ft²On request
Flat No F 702291 ft²On request
Flat No G 701291 ft²On request
Flat No G 702291 ft²On request
Flat No C 703291 ft²On request
Flat No C 704291 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Live availability, floor plans & today's price — on WhatsApp
03

RERA Trust Record

MahaRERA No.
P52000017468
Registered
2021-09-09
Litigation
None on record
Escrow Bank
IDBI BANK
Architect
Total FSI
5173
04

Buildings · 5 Wing(s)

Green Park Phase -Ii C Wing9 floors · — units
Green Park Phase -Ii D Wing9 floors · — units
Green Park Phase -Ii E Wing9 floors · — units
Green Park Phase -Ii F Wing9 floors · — units
Green Park Phase -Ii G Wing9 floors · — units
05

Land DNA · Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06

Location

📍 Mahad
0.000000000000000,0.000000000000000
▸ Explore map & Street View — for verified buyers
07

Promoter & Professionals

ASHISH MULCHANDBHAI AMINPartner
JAYANTIBHAI SHAMJIBHAI VASOYAPartner
09

Construction Progress

91% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Podiums (if any) 0%
10

Amenities

Electrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStreet LightingWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

📐 Unit floor plans📄 Official e-brochure💳 Payment plans · 20:80 · subvention · current offers

Shared on WhatsApp by our MahaRERA advisor — including the latest builder offers and payment schemes we don't list publicly.

💬 Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

14

More by Shreeji Associates

Shreejee MrugarchanaMulund West · Ready PossessionShreeji EternityMalad West · Under ConstructionShreeji DivineKharghar · Under ConstructionShreeji BlissMalad West · Sold OutShreeji FioraKandivali West · Under ConstructionShreeji TapovanMalad East · Under Construction
15

MahaRERA projects nearby in Mahad

CKC HUB136 unitsCloud 9101 unitsLUCKY HOUSE100 unitsNITYA NIRGUN ENCLAVE90 unitsSAI SHRUSTHI82 unitsKRANTIBHUMI COOPERATIVE HOUSING SOCIETY -SILVER HEIGHT62 unitsSKYLINE RESIDENCIES59 unitsIndraprashth58 unitsRAIGAD CITY C WING53 unitsSIYA 24 K PHASE II51 unitsShinde Arcade48 unitsJAI TULJABHAVANI SAHAKARI GRUHANIRMAN SANSTHA LTD44 units
?

Frequently Asked Questions

When is possession of GREEN PARK PHASE -II?

As per MahaRERA, proposed possession is Dec 2024.

Is GREEN PARK PHASE -II RERA-registered?

Yes — MahaRERA registration P52000017468, registered 2021-09-09. No litigations on record.

Who is the developer?

Shreeji Associates — 33 projects tracked on Mumbai Property Exchange. View their track record ▸

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.

SOURCE · MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA · RERA A51800043517 · EST. 1995
WhatsAppEnquire ▸
🎯 AI Matchmaker
Tell us what you want in Mahad — get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
✓ MahaRERA P52000016540★ Featured
The Wadhwa Group
Wadhwa Wise City, New Panvel
1 BHK, 2 BHK, 3 BHK · ₹16,946/sq.ft · Possession 2026-12-01 00:00:00
Learn more ›

📰 Latest Mumbai Property News

View all news →