Hubtown Seasons - B Wing

by Joynest Premises PrivateLimited Company
Certificate Signed P51800008552
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800008552
Registration No.
REA51800008223
Registration Date
2024-05-29
Developer
Joynest Premises PrivateLimited Company
Architect
Citygold Management Service Private Limited
Project Bank
HDFC BANK
Proposed Possession
2025-07-31
Revised Possession
2025-07-31
Extended Possession
2026-07-31
Total Units
53
Units Sold
31 (58%)
Buildings
1
Project Area
252.53 sq.m
Total FSI
5245.20
Approved FSI
868.96
MahaRERA QR
Hubtown Seasons - B Wing
MahaRERA — P51800008552
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors17
Sanctioned17
🏠Habitable14
🔢Total Units53
🏡Residential53
⬇️Basements2
🅿️Closed Parking77
📅Completion2024-07-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2Bhk 67.52999877929688 0 0 0
0%
2Bhk 92.02999877929688 0 0 0
0%
3Bhk 68.77999877929688 0 0 0
0%

Hubtown Seasons - B Wing

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 67.37 26 2 24
8%
2 BHK 92.03 15 11 4
73%
3 BHK 68.78 13 4 9
31%
3 BHK 84.38 1 0 1
0%
3 BHK 90.04 11 2 9
18%

Construction Progress

Hubtown Seasons - B Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing22%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure20%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.