📞 +91 98200 30685✉️
RERA: A51800043517

N G Platinum City

by J M G REALTORS PVT LTD Company
Certificate SignedP99000024280

Project Information

RERA Certificate No.
P99000024280
Registration No.
REA99000067638
Registration Date
2025-07-28
Developer
J M G REALTORS PVT LTD Company
Architect
Shah Gattani Consultants Divyesh Shah
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2024-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
167
Units Sold
147 (88%)
Buildings
5
Project Area
6200.00 sq.m
Total FSI
6192.45
Approved FSI
6192.45
MahaRERA QR
N G Platinum City
MahaRERA — P99000024280
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
🏠Habitable7
🔢Total Units30
🏡Residential30
🅿️Closed Parking1
📅Completion2023-12-31
🏗️Proposed Floors9
Sanctioned9
🏠Habitable7
🔢Total Units30
🏡Residential30
🅿️Closed Parking1
📅Completion2023-12-31
🏗️Proposed Floors9
Sanctioned9
🏠Habitable7
🔢Total Units30
🏡Residential30
🅿️Closed Parking1
📅Completion2023-12-31
🏗️Proposed Floors9
Sanctioned9
🏠Habitable7
🔢Total Units30
🏡Residential30
🅿️Closed Parking1
📅Completion2023-12-31
🏗️Proposed Floors9
Sanctioned9
🏠Habitable7
🔢Total Units47
🏡Residential47
🅿️Closed Parking1
📅Completion2023-12-31

Apartment Configurations

N G Platinum City Hh57

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.7830030
0%

N G Platinum City Hh60

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK34.7830030
0%

N G Platinum City Hi59

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.0523023
0%
1 BHK33.11707
0%
1 BHK33.48808
0%
1 BHK34.78808
0%
1RK22.35101
0%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk33.04999923706055000
0%
1Bhk33.11000061035156000
0%
1Bhk33.47999954223633000
0%
1Bhk34.779998779296875000
0%
1Rk22.350000381469727000
0%

Construction Progress

N G PLATINUM CITY HH57

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure12%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

N G PLATINUM CITY HH58

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure12%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

N G PLATINUM CITY HH60

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure12%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

N G PLATINUM CITY HH61

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure12%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

N G PLATINUM CITY HI59

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure12%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now