📞 +91 98200 30685 ✉️
RERA: A51800043517

Nebula Empress

by M/s Shiv Sai developer Others
Certificate Signed P51800054371
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800054371
Registration No.
REA51800150152
Registration Date
2024-01-18
Developer
M/s Shiv Sai developer Others
Architect
Ken Assist
Project Bank
HDFC BANK
Proposed Possession
2027-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
112
Units Sold
0 (0%)
Buildings
2
Project Area
710.70 sq.m
Total FSI
6218.56
Approved FSI
5548.31
MahaRERA QR
Nebula Empress
MahaRERA — P51800054371
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors21
Sanctioned21
🏠Habitable20
🔢Total Units41
🏡Residential40
🏢Non-Residential1
📅Completion2027-12-31
🏗️Proposed Floors21
Sanctioned21
🏠Habitable20
🔢Total Units71
🏡Residential71
📅Completion2027-12-31

Apartment Configurations

A Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.36 4 0 4
0%
2 BHK 53.03 1 0 1
0%
2 BHK 58.79 15 0 15
0%
3 BHK 107.78 4 0 4
0%
PAP 27.88 1 0 1
0%
REHAB UNITS 27.88 16 0 16
0%
Shop 83.39 1 0 1
0%

B Wing

Type Carpet (sq.ft) Total Booked Available Status
1RK 29.36 2 0 2
0%
AMENTIES 27.88 4 0 4
0%
PAP 27.88 22 0 22
0%
REHAB UNITS 27.88 46 0 46
0%
SOCIETY OFFICE 20.0 1 0 1
0%

Construction Progress

A Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.72%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.77%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises82%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises82%
Slabs of Super Structure82%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks82%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

B Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.72%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.77%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises82%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises82%
Slabs of Super Structure82%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks82%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 95%
Energy management
Fire Protection And Fire Safety Requirements 95%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.