RERA: A51800043517

PALAVA MILANO A,B,C,H,I,J

by Palava Dwellers Private Limited Company
Certificate Signed P51700015016
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700015016
Registration No.
REA51700031451
Registration Date
2021-09-09
Developer
Palava Dwellers Private Limited Company
Project Bank
YES BANK
Proposed Possession
2023-10-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
6
Project Area
4954.77 sq.m
Total FSI
30794.32
Approved FSI
27970.32
MahaRERA QR
PALAVA MILANO A,B,C,H,I,J
MahaRERA — P51700015016
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors19
Sanctioned19
🚗Open Parking9
🅿️Closed Parking96
📅Completion2023-10-30
🏗️Proposed Floors19
Sanctioned19
🚗Open Parking9
🅿️Closed Parking61
📅Completion2023-10-30
🏗️Proposed Floors19
Sanctioned19
🚗Open Parking9
🅿️Closed Parking96
📅Completion2023-10-30
🏗️Proposed Floors19
Sanctioned19
🚗Open Parking9
🅿️Closed Parking96
📅Completion2023-10-30
🏗️Proposed Floors19
Sanctioned19
🚗Open Parking9
🅿️Closed Parking61
📅Completion2023-10-30
🏗️Proposed Floors19
Sanctioned19
🚗Open Parking9
🅿️Closed Parking96
📅Completion2023-10-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk 37.06999969482422 0 0 0
0%
1 Bhk 39.47999954223633 0 0 0
0%
1 Bhk 39.68000030517578 0 0 0
0%
1 Bhk 39.7599983215332 0 0 0
0%
1 Bhk 47.189998626708984 0 0 0
0%
1Bhk 37.0 0 0 0
0%
1Bhk 37.06999969482422 0 0 0
0%
1Bhk 39.7599983215332 0 0 0
0%
2 Bhk Ultima 48.959999084472656 0 0 0
0%
2 Bhk Ultima 49.04999923706055 0 0 0
0%
2 Bhk Ultima 50.13999938964844 0 0 0
0%
2 Bhk Ultima 50.16999816894531 0 0 0
0%
2 Bhk Ultima 52.81999969482422 0 0 0
0%
2 Bhk Ultima 52.86000061035156 0 0 0
0%
2 Bhk Ultima 55.18000030517578 0 0 0
0%
2 Bhk Ultima 59.7400016784668 0 0 0
0%
2Bhk 52.86000061035156 0 0 0
0%
2Bhk Ultima 49.04999923706055 0 0 0
0%
2Bhk Ultima 50.16999816894531 0 0 0
0%
3 Bhk Optima 59.63999938964844 0 0 0
0%
3 Bhk Optima 59.65999984741211 0 0 0
0%
3 Bhk Optima 59.720001220703125 0 0 0
0%
3 Bhk Optima 59.7400016784668 0 0 0
0%

Milano A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 37.0 6 6 0
100%
1 BHK 37.07 58 56 2
97%
1 BHK 39.68 1 1 0
100%
1 BHK 39.76 1 1 0
100%
1 BHK 47.19 2 0 2
0%
2 BHK 52.86 1 1 0
100%
2 BHK ULTIMA 50.14 2 2 0
100%
2 BHK Ultima 50.17 32 21 11
66%
2 BHK ULTIMA 52.82 1 1 0
100%
3 BHK OPTIMA 59.64 1 1 0
100%

Milano B

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 39.48 2 0 2
0%
2 BHK Ultima 49.05 32 17 15
53%
2 BHK Ultima 50.17 1 0 1
0%
3 BHK OPTIMA 59.74 35 13 22
37%

Milano C

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 37.07 64 62 2
97%
1 BHK 39.76 2 2 0
100%
1 BHK 47.19 2 0 2
0%
2 BHK ULTIMA 50.17 34 18 16
53%
2 BHK ULTIMA 52.82 2 1 1
50%
3 BHK OPTIMA 59.64 1 1 0
100%

Milano H

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 37.07 64 63 1
98%
1 BHK 39.76 2 2 0
100%
1 BHK 47.19 2 0 2
0%
2 BHK ULTIMA 50.17 34 11 23
32%
2 BHK ULTIMA 52.86 2 0 2
0%
3 BHK OPTIMA 59.64 1 1 0
100%

Milano I

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 39.48 2 2 0
100%
2 BHK ULTIMA 48.96 7 7 0
100%
2 BHK ultima 49.05 25 18 7
72%
2 BHK Ultima 55.18 1 1 0
100%
2 BHK ULTIMA 59.74 33 25 8
76%
3 BHK OPTIMA 59.66 1 1 0
100%
3 BHK OPTIMA 59.72 1 1 0
100%

Milano J

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 37.0 8 8 0
100%
1 BHK 37.07 56 55 1
98%
1 BHK 39.68 1 1 0
100%
1 BHK 39.76 1 1 0
100%
1 BHK 47.19 2 0 2
0%
2 BHK ULTIMA 50.14 3 3 0
100%
2 BHK Ultima 50.17 31 22 9
71%
2 BHK ULTIMA 52.86 2 0 2
0%
3 BHK OPTIMA 59.64 1 1 0
100%

Construction Progress

MILANO A

Basement (if any)100%

Milano A

Excavation100%

MILANO A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Milano A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

MILANO A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Milano A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%

MILANO A

Plinth100%
Podiums (if any) 0%

Milano A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

MILANO A

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Milano A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

MILANO A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Milano A

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

MILANO B

Basement (if any)100%

Milano B

Excavation100%

MILANO B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Milano B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

MILANO B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Milano B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%

MILANO B

Plinth100%
Podiums (if any) 0%

Milano B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

MILANO B

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Milano B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

MILANO B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Milano B

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

MILANO C

Basement (if any)100%

Milano C

Excavation100%

MILANO C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Milano C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

MILANO C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Milano C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%

MILANO C

Plinth100%
Podiums (if any) 0%

Milano C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

MILANO C

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Milano C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

MILANO C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Milano C

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

MILANO H

Basement (if any)100%

Milano H

Excavation100%

MILANO H

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Milano H

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

MILANO H

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Milano H

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%

MILANO H

Plinth100%
Podiums (if any) 0%

Milano H

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

MILANO H

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Milano H

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

MILANO H

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Milano H

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

MILANO I

Basement (if any)100%

Milano I

Excavation100%

MILANO I

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Milano I

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

MILANO I

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Milano I

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%

MILANO I

Plinth100%
Podiums (if any) 0%

Milano I

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

MILANO I

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Milano I

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

MILANO I

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Milano I

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

MILANO J

Basement (if any)100%

Milano J

Excavation100%

MILANO J

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Milano J

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

MILANO J

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Milano J

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%

MILANO J

Plinth100%
Podiums (if any) 0%

Milano J

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

MILANO J

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Milano J

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

MILANO J

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Milano J

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Closing Parking 100%
Clubhouse
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Sports Complex
Storm Water Drains 100%
Street Lighting 100%
Temple
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.