📞 +91 98200 30685 ✉️
RERA: A51800043517

PALAVA MILANO E, F

by Palava Dwellers Private Limited Company
Certificate Signed P51700011629
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700011629
Registration No.
REA51700021118
Registration Date
2021-09-09
Developer
Palava Dwellers Private Limited Company
Project Bank
YES BANK
Proposed Possession
2023-03-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
2657.00 sq.m
Total FSI
14658.15
Approved FSI
13325.15
MahaRERA QR
PALAVA MILANO E, F
MahaRERA — P51700011629
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors18
Sanctioned18
🚗Open Parking9
🅿️Closed Parking98
📅Completion2023-03-30
🏗️Proposed Floors18
Sanctioned18
🚗Open Parking9
🅿️Closed Parking98
📅Completion2023-03-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2Bhk 45.52000045776367 0 0 0
0%
2Bhk 48.63999938964844 0 0 0
0%
2Bhk 48.66999816894531 0 0 0
0%
2Bhk 50.349998474121094 0 0 0
0%
2Bhk 51.95000076293945 0 0 0
0%
2Bhk 53.11000061035156 0 0 0
0%
2Bhk 53.93000030517578 0 0 0
0%
2Bhk 54.720001220703125 0 0 0
0%
2Bhk 56.38999938964844 0 0 0
0%
2Bhk 57.29999923706055 0 0 0
0%
2Bhk 57.599998474121094 0 0 0
0%
2Bhk 57.689998626708984 0 0 0
0%
2Bhkoptima 54.63999938964844 0 0 0
0%
2Bhkultima 53.08000183105469 0 0 0
0%
2Bhkultima 57.63999938964844 0 0 0
0%
2Bhkultima 61.5 0 0 0
0%
3Bhk 73.62000274658203 0 0 0
0%

Milano E

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 45.52 1 0 1
0%
2 BHK 48.64 1 0 1
0%
2 BHK 48.67 1 0 1
0%
2 BHK 50.35 13 0 13
0%
2 BHK 51.95 16 0 16
0%
2 BHK 53.11 13 0 13
0%
2 BHK 53.93 1 0 1
0%
2 BHK 54.72 1 1 0
100%
2 BHK 56.39 1 1 0
100%
2 BHK 57.3 3 0 3
0%
2 BHK 57.6 1 1 0
100%
2 BHK 57.69 18 18 0
100%
2 BHKOptima 54.64 2 2 0
100%
2 BHKUltima 53.08 1 1 0
100%
2 BHKUltima 57.64 28 28 0
100%
2 BHKUltima 61.5 2 2 0
100%
3 BHK 73.62 2 0 2
0%

Construction Progress

MILANO E

Basement (if any)100%

Milano E

Excavation100%

MILANO E

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Milano E

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

MILANO E

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Milano E

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing70%

MILANO E

Plinth100%
Podiums (if any) 0%

Milano E

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

MILANO E

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Milano E

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

MILANO E

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Milano E

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

MILANO F

Basement (if any)100%

Milano F

Excavation100%

MILANO F

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Milano F

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

MILANO F

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Milano F

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing70%

MILANO F

Plinth100%
Podiums (if any) 0%

Milano F

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

MILANO F

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Milano F

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

MILANO F

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Milano F

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Closing Parking 100%
Club House
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Sports Complex
Storm Water Drains 100%
Street Lighting 100%
Temple
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.