📞 +91 98200 30685 ✉️
RERA: A51800043517

Park Way

by Om Sai Ganesh Builders & Developers Pvt Ltd Company
Certificate Signed P51900047931
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51900047931
Registration No.
REA51900121343
Registration Date
2022-12-01
Developer
Om Sai Ganesh Builders & Developers Pvt Ltd Company
Architect
B.N.Shah & Associates
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2027-03-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
923.08 sq.m
Total FSI
4863.07
Approved FSI
4863.07
MahaRERA QR
Park Way
MahaRERA — P51900047931
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors31
Sanctioned31
⬇️Basements1
🅿️Closed Parking69
📅Completion2027-03-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 25.290000915527344 0 0 0
0%
1Bhk 45.20000076293945 0 0 0
0%
1Bhk 47.849998474121094 0 0 0
0%
1Bhk 51.91999816894531 0 0 0
0%
2Bhk 70.5 0 0 0
0%
2Bhk 79.91000366210938 0 0 0
0%
3Bhk 95.80999755859375 0 0 0
0%

Park Way

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 25.29 4 1 3
25%
1 BHK 45.2 1 0 1
0%
1 BHK 47.85 1 1 0
100%
1 BHK 51.92 1 0 1
0%
2 BHK 70.5 16 5 11
31%
2 BHK 79.91 1 0 1
0%
3 BHK 95.81 1 0 1
0%

Construction Progress

PARK WAY

Basement (if any)100%

Park Way

Excavation100%

PARK WAY

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Park Way

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%

PARK WAY

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Park Way

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

PARK WAY

Plinth100%
Podiums (if any) 100%

Park Way

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%

PARK WAY

Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%

Park Way

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.95%

PARK WAY

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%

Park Way

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 75%
Energy management
Fire Protection And Fire Safety Requirements 85%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 30%
Solid Waste Management And Disposal
Storm Water Drains 20%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.