Project Information

RERA Certificate No.
P51800004140
Registration No.
REA51800010662
Registration Date
2017-08-08
Developer
Royal Palms India Pvt. Ltd. Company
Architect
Vinayak Lomate
Project Bank
BHARAT COOPERATIVE BANK MUMBAI LIMITED
Proposed Possession
2018-02-28
Revised Possession
2018-02-28
Extended Possession
2019-02-28
Units Sold
0
Buildings
1
Project Area
2384.00 sq.m
Total FSI
2384.25
Approved FSI
2384.25
MahaRERA QR
Piccadilly IV
MahaRERA — P51800004140
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors4
Sanctioned4
🚗Open Parking44
🅿️Closed Parking1
📅Completion2019-02-28

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
B 39.650001525878906 0 0 0
0%
C 41.060001373291016 0 0 0
0%
Type A 17.579999923706055 0 0 0
0%

Piccadilly Iv

Type Carpet (sq.ft) Total Booked Available Status
B 39.65 27 26 1
96%
C 41.06 12 12 0
100%
TYPE A 17.58 3 3 0
100%

Construction Progress

Piccadilly IV

Basement (if any)0%

Piccadilly Iv

Excavation100%

Piccadilly IV

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%

Piccadilly Iv

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate20%

Piccadilly IV

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%

Piccadilly Iv

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%
Overall Percentage of Completion of the work done For the entire Building /Wing59%

Piccadilly IV

Plinth0%
Podiums (if any) 0%

Piccadilly Iv

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises95%

Piccadilly IV

Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%

Piccadilly Iv

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.95%

Piccadilly IV

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%

Piccadilly Iv

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements 20%
Landscaping & Tree Planting 95%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 80%
Solid Waste Management And Disposal 80%
Storm Water Drains
Street Lighting 80%
Treatment And Disposal Of Sewage And Sullage Water 80%
Water Conservation, Rain water Harvesting 20%
Water Supply 80%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.