PLATINUM TOWER - 31

by MANAS GRUHPRAVESH LLP Others
Certificate Signed P51800001759
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800001759
Registration No.
REA51800008248
Registration Date
2021-09-09
Developer
MANAS GRUHPRAVESH LLP Others
Architect
Space Moulders
Project Bank
ICICI BANK LIMITED
Proposed Possession
2022-06-30
Revised Possession
2022-06-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
874.63 sq.m
Total FSI
6121.00
Approved FSI
6121.00
MahaRERA QR
PLATINUM TOWER - 31
MahaRERA — P51800001759
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors20
Sanctioned20
⬇️Basements3
🅿️Closed Parking66
📅Completion2021-06-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
Residential 28.059999465942383 0 0 0
0%
Residential 30.010000228881836 0 0 0
0%
Residential 40.40999984741211 0 0 0
0%
Residential 53.880001068115234 0 0 0
0%

Platinum Tower 31

Type Carpet (sq.ft) Total Booked Available Status
RESIDENTIAL 28.06 14 14 0
100%
RESIDENTIAL 30.01 32 32 0
100%
RESIDENTIAL 40.41 13 13 0
100%
RESIDENTIAL 53.88 24 24 0
100%

Construction Progress

PLATINUM TOWER 31

Basement (if any)100%

Platinum Tower 31

Excavation100%

PLATINUM TOWER 31

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%

Platinum Tower 31

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate61%

PLATINUM TOWER 31

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.61%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Platinum Tower 31

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

PLATINUM TOWER 31

Plinth100%
Podiums (if any) 0%

Platinum Tower 31

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises80%

PLATINUM TOWER 31

Sanitary Fittings within the flats / premises80%
Slabs of Super Structure100%

Platinum Tower 31

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

PLATINUM TOWER 31

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Platinum Tower 31

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing98%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 95%
Energy management
Fire Protection And Fire Safety Requirements 95%
Landscaping & Tree Planting 90%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 95%
Solid Waste Management And Disposal
Storm Water Drains 95%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 100%
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.