Poonam Park View Phase II

πŸ“ Global City, Palghar Β· 401303
342
Units
2021
Possession
4
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Jun 2021
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
1 BHK346–385 ftΒ²On request
Shop127–406 ftΒ²On request
2 BHK488–646 ftΒ²On request
Comm470–850 ftΒ²On request
3 BHK686–927 ftΒ²On request
Comm And1,530 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P99000016911
Registered
2020-06-20
Litigation
None on record
Escrow Bank
KOTAK MAHINDRA BANK LIMITED
Architect
Shah Gattani Consultants
Total FSI
16920
04

Buildings Β· 4 Wing(s)

F Wing17 floors Β· β€” units
G Wing17 floors Β· β€” units
H Wing17 floors Β· β€” units
I Wing17 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Global City
19.693558100000000,72.765518400000020
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

ASHWIN MANEK MEHTAβ€”
MANEK JUGRAJ MEHTAβ€”
PABAL HOUSING PVT. LTDβ€”
09

Construction Progress

100% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
10

Amenities

Electrical Meter Room, Sub-Station, Receiving StationEnergy managementFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
14

More by Poonam Homemaker

Poonam PolarisAndheri West Β· Under ConstructionSky CityVirar Β· Under ConstructionPoonam VistaVirar Β· Ready PossessionPoonam Park ViewVirar Β· Sold OutPoonam ImperialVirar Β· Ready PossessionPoonam HeightsVirar Β· Sold Out
15

MahaRERA projects nearby in Global City

Redbricks - Wing AEVERSHINE AMAVI 303 PHASE 1EVERSHINE AMAVI 303 PHASE 2EVERSHINE 36 TURNER ROADMahavir Darshan
?

Frequently Asked Questions

When is possession of POONAM PARK VIEW PHASE II?

As per MahaRERA, proposed possession is Jun 2021.

Is POONAM PARK VIEW PHASE II RERA-registered?

Yes β€” MahaRERA registration P99000016911, registered 2020-06-20. No litigations on record.

Who is the developer?

Poonam Homemaker β€” 13 projects tracked on Mumbai Property Exchange. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Global City β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P52000016540β˜… Featured
The Wadhwa Group
Wadhwa Wise City, New Panvel
1 BHK, 2 BHK, 3 BHK Β· β‚Ή16,946/sq.ft Β· Possession 2026-12-01 00:00:00
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’