Evershine Amavi 303 Phase 2

📍 Global City Virar West, Palghar · 401303
244
Units
2023
Possession
4
Buildings
Certificate Signed
Status
Lifecycle requires verification

Ask an advisor to verify the current project and inventory status.

Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01

Possession Timeline

Proposed
Dec 2023
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
Shop139–356 ft²On request
1 BHK413 ft²On request
2 BHK550–645 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor
03

RERA Trust Record

MahaRERA No.
P99000024860
Registered
2021-09-08
Litigation
No reported in source
Escrow Bank
HDFC BANK
Architect
Total FSI
12624
04

Buildings · 4 Wing(s)

Building No 1016 floors · — units
Building No 1116 floors · — units
Building No 1216 floors · — units
Building No 1316 floors · — units
05

Land DNA · Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06

Location

📍 Global City Virar West
19.4722599,72.8037783
▸ Explore map & Street View — for verified buyers
07

Promoter & Professionals

SANTOSH RAJKUMAR LUDHANIPartner
09

Construction Progress

100% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Plinth100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
10

Amenities

Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationEnergy managementFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater Supply
12

Talk to our MahaRERA advisor

🏠 Discuss what you're looking for📍 Locality & project guidance🤝 Speak to a specialist

Tell our MahaRERA advisor what you need and they'll guide you on this project.

💬 Verify current project inventory
08

Property Rates in Global City Virar West

Residential · Sale
₹6,000–10,000/sqft
Commercial · Sale
₹6,000–7,500/sqft
2 BHK · Rent
₹10,000–20,000/mo
14

More by Evershine Developers

15

MahaRERA projects nearby in Global City Virar West

?

Frequently Asked Questions

When is possession of Evershine Amavi 303 Phase 2?

As per MahaRERA, proposed possession is Dec 2023.

Is Evershine Amavi 303 Phase 2 RERA-registered?

Yes — MahaRERA registration P99000024860, registered 2021-09-08. The current MahaRERA source record reports no litigations.

Who is the developer?

Evershine Developers — 21 projects tracked on Mumbai Property Exchange. View their track record ▸

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.

SOURCE · MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA · RERA A51800043517 · EST. 1995
WhatsAppEnquire ▸
🎯 AI Matchmaker
Tell us what you want in Global City Virar West — get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
Sponsored
New launch
Codename Capital World, Thane West
New launch in Thane West — ₹14,382/sq.ft
View project ›

📰 Latest Mumbai Property News

View all news →