List PropertyWhatsApp
New ProjectsBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your PropertyπŸ’¬ WhatsApp Us
🏠 Mumbai property advisory & dataOperating since 1995βœ“ MahaRERA A51800043517βœ“ RERA-verified project data🟒 We reply in minutes on WhatsApp
V
βœ“ MahaRERA P99000054244βœ“ Clear

Vinay Unique Residency Bldg No 10 Known As - Sky by Jasamrit Estates

πŸ“ Virar West, Palghar Β· 401303
497
Units
2029
Possession
4
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2029
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
1 BHK314–446 ftΒ²On request
2 BHK421–546 ftΒ²On request
3 BHK822–921 ftΒ²On request
Shop163–1,052 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P99000054244
Registered
2024-01-10
Litigation
None on record
Escrow Bank
AXIS BANK
Architect
Encon Mr Sanjay Narang
Total FSI
40678
04

Buildings Β· 4 Wing(s)

Vinay Unique Residency Bldg No 10 A Wing29 floors Β· β€” units
Vinay Unique Residency Bldg No 10 B Wing29 floors Β· β€” units
Vinay Unique Residency Bldg No 10 C Wing29 floors Β· β€” units
Vinay Unique Residency Bldg No 10 I Wing29 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Virar West
19.452214000000000,72.797845000000000
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

ANUP ASHOK MEHTADirector
JAYESHKUMAR VINAYCHAND DOSHIManaging Director
MEET SHAILESH DOSHIDirector
PIYUSH ASHOK MEHTADirector
09

Construction Progress

19% avg
Excavation100%
Basement (if any)50%
Plinth50%
X number of Basement(s) and Plinth50%
Overall Percentage of Completion of the work done For the entire Building /Wing15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
10

Amenities

Electrical Meter Room, Sub-Station, Receiving StationEnergy managementFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
15

MahaRERA projects nearby in Virar West

MAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19, 23A, 26, 27901 unitsYASHWANT AVENUE 2209 unitsVIVA CITY - A3140 unitsVIVA CITY - A4138 unitsYASHWANT PRESTIGE112 unitsSHANTI NIWAS108 unitsMAHAVIR ASHISH CO-OPERATIVE HOUSING SOCIETY LTD78 unitsYASHWANT CIRCLE70 unitsAvanti Heights70 unitsSHREE GAYATRI CHSL56 unitsHIRUBAI RESIDENCY39 unitsSHREE SHIVKRUPA CO OPERATIVE HOUSING SOCIETY LIMITED31 units
?

Frequently Asked Questions

When is possession of VINAY UNIQUE RESIDENCY BLDG NO 10 KNOWN AS-SKY?

As per MahaRERA, proposed possession is Dec 2029.

Is VINAY UNIQUE RESIDENCY BLDG NO 10 KNOWN AS-SKY RERA-registered?

Yes β€” MahaRERA registration P99000054244, registered 2024-01-10. No litigations on record.

Who is the developer?

Jasamrit Estates View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Virar West β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P51900006299β˜… Featured
Godrej Properties
Godrej Avenue Eleven B, Mahalaxmi
4 BHK Β· β‚Ή69,000/sq.ft Β· Possession Jan 2029
Learn more β€Ί

πŸ“° Latest Mumbai Property News