Sai Proviso Atlantis Phase I

by Sai Proviso Buildcon LLP Others
Certificate Signed P52000051330
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P52000051330
Registration No.
REA52000139174
Registration Date
2023-06-08
Developer
Sai Proviso Buildcon LLP Others
Architect
The Firm
Project Bank
INDIAN OVERSEAS BANK
Proposed Possession
2028-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
11330.00 sq.m
Total FSI
14142.97
Approved FSI
13192.97
MahaRERA QR
Sai Proviso Atlantis Phase I
MahaRERA — P52000051330
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors35
Sanctioned35
🚗Open Parking40
🅿️Closed Parking131
📅Completion2028-12-31
🏗️Proposed Floors2
Sanctioned2
🅿️Closed Parking1
📅Completion2028-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 29.969999313354492 0 0 0
0%
2Bhk 49.90999984741211 0 0 0
0%
Club House 158.91000366210938 0 0 0
0%

Bldg No 3 - Athena

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.97 106 96 10
91%
2 BHK 49.91 112 55 57
49%

Club Etihad

Type Carpet (sq.ft) Total Booked Available Status
Club House 158.91 0 0 0
0%

Construction Progress

Bldg No 3 - Athena

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth50%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure9%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 50%

Club Etihad

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Plinth60%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Gymnasium
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Society Office
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.