Project Information

RERA Certificate No.
P51700000363
Registration No.
REA51700003969
Registration Date
2021-09-10
Developer
Rajesh Dharamvir Gulati Individual
Architect
Soyuz Talib Architects Pvt Ltd
Project Bank
AXIS BANK
Proposed Possession
2021-12-30
Revised Possession
2021-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
2198.73 sq.m
Total FSI
3298.00
Approved FSI
3298.00
MahaRERA QR
Satyam Mayfair
MahaRERA — P51700000363
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors16
Sanctioned16
🚗Open Parking30
🅿️Closed Parking17
📅Completion2020-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2Bhk 41.650001525878906 0 0 0
0%
2Bhk 42.119998931884766 0 0 0
0%
2Bhk 43.31999969482422 0 0 0
0%
2Bhk 50.02000045776367 0 0 0
0%
3Bhk 59.75 0 0 0
0%
3Bhk 62.849998474121094 0 0 0
0%
Shop 25.200000762939453 0 0 0
0%
Shop 28.209999084472656 0 0 0
0%
Shop 28.670000076293945 0 0 0
0%
Shop 34.22999954223633 0 0 0
0%
Shop 38.900001525878906 0 0 0
0%
Shop 40.79999923706055 0 0 0
0%

Satyam Mayfair

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 41.65 10 7 3
70%
2 BHK 42.12 14 13 1
93%
2 BHK 43.32 10 5 5
50%
2 BHK 50.02 8 6 2
75%
3 BHK 59.75 6 5 1
83%
3 BHK 62.85 8 5 3
62%
SHOP 25.2 4 0 4
0%
SHOP 28.21 2 1 1
50%
SHOP 28.67 2 0 2
0%
SHOP 34.23 3 2 1
67%
SHOP 38.9 1 0 1
0%
SHOP 40.8 1 0 1
0%

Construction Progress

SATYAM MAYFAIR

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
CHILDRENS PLAY AREA 100%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements 100%
GYMNASIUM 100%
INDOOR GAMES 100%
LANDSCAPED GARDEN SITOUTS 100%
Landscaping & Tree Planting 100%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting
SWIMMING POOL 100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 100%
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.