SAYBA ARCADIA

by STAR EMPIRE Partnership
Certificate Signed P51800055257
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800055257
Registration No.
REA51800153396
Registration Date
2024-03-18
Developer
STAR EMPIRE Partnership
Project Bank
PUNJAB NATIONAL BANK
Proposed Possession
2026-03-31
Total Units
116
Units Sold
48 (41%)
Project Area
1220.68 sq.m
Total FSI
4949.75
Approved FSI
1628.22
MahaRERA QR
SAYBA ARCADIA
MahaRERA — P51800055257
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
Sanctioned8
🏠Habitable8
🔢Total Units30
🏡Residential28
🏢Non-Residential2
🅿️Closed Parking5
📅Completion2026-03-31
🏗️Proposed Floors8
Sanctioned8
🏠Habitable7
🔢Total Units27
🏡Residential27
🅿️Closed Parking5
📅Completion2026-03-31
🏗️Proposed Floors8
Sanctioned8
🏠Habitable8
🔢Total Units31
🏡Residential28
🏢Non-Residential3
🅿️Closed Parking6
📅Completion2026-03-31
🏗️Proposed Floors8
Sanctioned8
🏠Habitable8
🔢Total Units28
🏡Residential21
🏢Non-Residential7
🅿️Closed Parking6
📅Completion2026-03-31

Apartment Configurations

A Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 35.83 7 0 7
0%
1 BHK 37.71 7 0 7
0%
1 BHK 39.63 7 0 7
0%
1 BHK 40.49 7 0 7
0%
Shop 17.2 1 0 1
0%
Shop 17.44 1 0 1
0%
Shop 25.58 1 0 1
0%

B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 35.81 1 0 1
0%
1 BHK 37.71 5 0 5
0%
1 BHK 39.63 6 0 6
0%
1 BHK 40.05 6 0 6
0%
1 BHK 40.25 7 0 7
0%
1 BHK 40.59 1 0 1
0%
1 BHK 53.44 1 0 1
0%
Shop 13.15 1 0 1
0%
Shop 22.69 1 0 1
0%
Shop 24.26 1 0 1
0%
Shop 36.59 1 0 1
0%

C Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 34.07 1 0 1
0%
1 BHK 35.24 1 0 1
0%
1 BHK 38.22 1 0 1
0%
1 BHK 38.97 6 0 6
0%
1 BHK 41.19 6 0 6
0%
1 BHK 41.45 6 0 6
0%
1 BHK 46.73 7 0 7
0%

D Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 40.55 7 0 7
0%
1 BHK 41.45 7 0 7
0%
1 BHK 47.65 7 0 7
0%
Shop 15.52 1 0 1
0%
Shop 15.7 1 0 1
0%
Shop 17.76 1 0 1
0%
Shop 21.57 1 0 1
0%
Shop 23.38 1 0 1
0%

Construction Progress

A WING

Basement (if any)100%

A Wing

Excavation100%

A WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

A Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

A WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%

A Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises30%
Overall Percentage of Completion of the work done For the entire Building /Wing51%

A WING

Plinth100%
Podiums (if any) 0%

A Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

A WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

A Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90%

A WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

A Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure90%

B WING

Basement (if any)100%

B Wing

Excavation100%

B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%

B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises30%
Overall Percentage of Completion of the work done For the entire Building /Wing51%

B WING

Plinth100%
Podiums (if any) 0%

B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

B WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90%

B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

B Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure90%

C WING

Basement (if any)100%

C Wing

Excavation100%

C WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

C Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

C WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%

C Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises30%
Overall Percentage of Completion of the work done For the entire Building /Wing51%

C WING

Plinth100%
Podiums (if any) 0%

C Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

C WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

C Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90%

C WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

C Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure90%

D WING

Basement (if any)100%

D Wing

Excavation100%

D WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

D Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

D WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%

D Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises30%
Overall Percentage of Completion of the work done For the entire Building /Wing51%

D WING

Plinth100%
Podiums (if any) 0%

D Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

D WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

D Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90%

D WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

D Wing

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure90%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal 90%
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.