RERA: A51800043517

SEASONS

by SHIV SAMARTH ENTERPRISES Partnership
Certificate Signed P99000066568
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P99000066568
Registration No.
REA99000156977
Registration Date
2024-06-11
Developer
SHIV SAMARTH ENTERPRISES Partnership
Architect
We Design
Project Bank
FEDERAL BANK
Proposed Possession
2032-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
3976.42 sq.m
Total FSI
40875.71
Approved FSI
15361.13
MahaRERA QR
SEASONS
MahaRERA — P99000066568
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors3
Sanctioned3
🅿️Closed Parking10
📅Completion2030-12-31
🏗️Proposed Floors25
Sanctioned25
🅿️Closed Parking94
📅Completion2029-12-31
🏗️Proposed Floors3
Sanctioned3
🅿️Closed Parking6
📅Completion2031-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 27.610000610351562 0 0 0
0%
1Bhk 27.90999984741211 0 0 0
0%
1Bhk 28.450000762939453 0 0 0
0%
1Bhk 28.540000915527344 0 0 0
0%
2Bhk 42.52000045776367 0 0 0
0%

Autumn - Building No 1 B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 27.61 1 0 1
0%

Springs -Building No 1 A Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 27.91 91 10 81
11%
1 BHK 28.54 87 3 84
3%
2 BHK 42.52 91 10 81
11%

Winter - Building No 1 C Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 28.45 1 0 1
0%

Construction Progress

AUTUMN - BUILDING NO 1 B WING

Basement (if any)0%

Autumn - Building No 1 B Wing

Excavation0%

AUTUMN - BUILDING NO 1 B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Autumn - Building No 1 B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

AUTUMN - BUILDING NO 1 B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Autumn - Building No 1 B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

AUTUMN - BUILDING NO 1 B WING

Plinth0%
Podiums (if any) 0%

Autumn - Building No 1 B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

AUTUMN - BUILDING NO 1 B WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Autumn - Building No 1 B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

AUTUMN - BUILDING NO 1 B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Autumn - Building No 1 B Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

SPRINGS -BUILDING NO 1 A WING

Basement (if any)100%

Springs -Building No 1 A Wing

Excavation100%

SPRINGS -BUILDING NO 1 A WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Springs -Building No 1 A Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

SPRINGS -BUILDING NO 1 A WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Springs -Building No 1 A Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

SPRINGS -BUILDING NO 1 A WING

Plinth100%
Podiums (if any) 0%

Springs -Building No 1 A Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

SPRINGS -BUILDING NO 1 A WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Springs -Building No 1 A Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

SPRINGS -BUILDING NO 1 A WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Springs -Building No 1 A Wing

Stilt Floor95%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

WINTER - BUILDING NO 1 C WING

Basement (if any)0%

Winter - Building No 1 C Wing

Excavation0%

WINTER - BUILDING NO 1 C WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Winter - Building No 1 C Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WINTER - BUILDING NO 1 C WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Winter - Building No 1 C Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

WINTER - BUILDING NO 1 C WING

Plinth0%
Podiums (if any) 0%

Winter - Building No 1 C Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WINTER - BUILDING NO 1 C WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Winter - Building No 1 C Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

WINTER - BUILDING NO 1 C WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Winter - Building No 1 C Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.