RERA: A51800043517

SUNSHINE GREEN PARK PHASE -3

by SHantee Homes Realty LLP Partnership
Certificate SignedP99000017859

Project Information

RERA Certificate No.
P99000017859
Registration No.
REA99000042872
Registration Date
2020-06-23
Developer
SHantee Homes Realty LLP Partnership
Architect
Encon
Project Bank
AU SMALL FINANCE BANK LIMITED
Proposed Possession
2022-06-30
Revised Possession
1900-01-01
Extended Possession
2026-12-31
Units Sold
0
Buildings
2
Project Area
2032.64 sq.m
Total FSI
6682.64
Approved FSI
5669.83
MahaRERA QR
SUNSHINE GREEN PARK PHASE -3
MahaRERA — P99000017859
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
Sanctioned5
🚗Open Parking12
📅Completion2021-12-31
🏗️Proposed Floors12
Sanctioned12
🚗Open Parking12
📅Completion2020-12-31

Apartment Configurations

Proposed Building

TypeCarpet (sq.ft)TotalBookedAvailableStatus
UNIT19.0772072
0%
UNIT31.39404
0%

Sunshing Green Park Bldg No 08

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK36.3226917
35%
1RK19.07724725
65%
1RK24.4981484
14%
1RK35.95716
14%
2RK24.85404
0%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk36.31999969482422000
0%
1Rk19.06999969482422000
0%
1Rk24.399999618530273000
0%
1Rk35.95000076293945000
0%
2Rk24.850000381469727000
0%
Unit19.06999969482422000
0%
Unit31.389999389648438000
0%

Construction Progress

PROPOSED BUILDING

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Proposed Building

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

SUNSHING GREEN PARK BLDG NO 08

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Sunshing Green Park Bldg No 08

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises90%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space40%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management
Fire Protection And Fire Safety Requirements100%
Landscaping & Tree Planting50%
Open Parking20%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Solid Waste Management And Disposal
Storm Water Drains80%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting60%
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.